Energy Projects Near You

Land Adjacent to Taw Valley Creamery (22 MW solar farm)

Land Adjacent to Taw Valley Creamery is a 22 MW solar farm project in West Devon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 8 January 2016; the record was last updated on 27 May 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

22 MWsolar farm
refusedstatus in REPD
27 May 2016record last updated
West Devoncouncil area

Planning timeline

DateStage
6 October 2014Application submitted
8 January 2016Refused by the planning authority

Project details

Technology
solar farm
Capacity
22 MW
Status (REPD)
refused
Record last updated
27 May 2016
Operator or applicant
Kinetica Energy
Planning authority
West Devon
Planning application reference
01132/2014
Site area
58.0 ha
Address (REPD)
Land Adjacent to Taw Valley Creamery, North Tawton
Council area (by location)
West Devon
Time to decision
66 weeks
REPD reference
4720

Who decides

ApplicationsWest DevonUK
Decided applications (solar, wind, battery)1810,236
Refused7 (39%)19%
Solar refused3 of 1212%
Onshore wind refused3 of 345%
Battery storage refused1 of 316%
Median time from submission to decision19.2 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
North Tawton Solar Farmsolar farm5refused0.4
North Tawton Primary Substationbattery storage30approved, not built0.9
Den Brookwind farm18operational3.5
Two Post Lanesolar farm12operational4.8
Land at Martin Farmsolar farm5approved, not built8.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.7886, -3.9152).