Two Post Lane (12 MW solar farm)

Two Post Lane is a 12 MW solar farm project in West Devon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 January 2022; the record was last updated on 22 June 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12 MWsolar farm
operationalstatus in REPD
22 June 2023record last updated
West Devoncouncil area

Planning timeline

DateStage
4 February 2020Application submitted
4 May 2020Planning permission granted
1 January 2022Operational

Project details

Technology
solar farm
Capacity
12 MW
Status (REPD)
operational
Record last updated
22 June 2023
Operator or applicant
Solar South West
Planning authority
West Devon
Planning application reference
0362/20/FUL
Site area
18.4 ha
Address (REPD)
Two Post Lane, Spreyton, South Tawton, Crediton, Devon
Council area (by location)
West Devon
Time to decision
13 weeks
REPD reference
7781

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsWest DevonUK
Decided applications (solar, wind, battery)1810,236
Refused7 (39%)19%
Solar refused3 of 1212%
Onshore wind refused3 of 345%
Battery storage refused1 of 316%
Median time from submission to decision19.2 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Den Brookwind farm18operational2.9
Land at Martin Farmsolar farm5approved, not built3.7
Land Adjacent to Taw Valley Creamerysolar farm22refused4.8
North Tawton Solar Farmsolar farm5refused5.2
North Tawton Primary Substationbattery storage30approved, not built5.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.7545, -3.8731).