Energy Projects Near You

Den Brook (18 MW wind farm)

Den Brook is an 18 MW wind farm project in West Devon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 17 November 2016; the record was last updated on 30 November 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18 MWwind farm
operationalstatus in REPD
30 November 2016record last updated
West Devoncouncil area

Planning timeline

DateStage
10 November 2005Application submitted
2 March 2006Refused by the planning authority
21 March 2007Planning permission granted
27 August 2015Construction started
17 November 2016Operational

Project details

Technology
wind farm
Capacity
18 MW
Status (REPD)
operational
Record last updated
30 November 2016
Operator or applicant
Aviva
Planning authority
West Devon
Planning application reference
8250/2005/OKE
Appeal reference
APP/Q1153/A/06/2017162/NWF
Turbines
9
Address (REPD)
Den Brook, West Devon
Council area (by location)
West Devon
Time to decision
71 weeks
REPD reference
4266

Who decides

ApplicationsWest DevonUK
Decided applications (solar, wind, battery)1810,236
Refused7 (39%)19%
Solar refused3 of 1212%
Onshore wind refused3 of 345%
Battery storage refused1 of 316%
Median time from submission to decision19.2 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Two Post Lanesolar farm12operational2.9
Land Adjacent to Taw Valley Creamerysolar farm22refused3.5
North Tawton Primary Substationbattery storage30approved, not built3.7
North Tawton Solar Farmsolar farm5refused3.8
Land at Martin Farmsolar farm5approved, not built6.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.7801, -3.8666).