Energy Projects Near You

Solar, wind and battery projects near Winkleigh (EX19)

8 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of EX19 (Torridge): 5 approved but not yet running, 3 operational. The largest live scheme is Coldharbour Farm, Ashreigney (50 MW solar farm, approved on 19 September 2023, not yet built), 2.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8projects within 10 km
0awaiting a decision
5approved, not running
3operational

Projects within 10 km of EX19

Projects of 1 MW and more (5)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Coldharbour Farm, Ashreigneysolar farmsolar farm50approved, not builtupdated Jun 2026Jul 2021granted Sep 2023Jun 2026Torridge2.6
Beaford Brook Solar Parksolar farmsolar farm5.2operationalupdated Jun 2013Jul 2012granted Dec 2012Jun 2013Torridge5.5
Crockers Helesolar farmsolar farm1.3operationalupdated Mar 2014Nov 2012granted Feb 2013Mar 2014West Devon7.5
Deptford Farm, Ebberley Hill Solar Farmsolar farmsolar farm27.8approved, not builtupdated Feb 2026Dec 2023refused Jul 2024Feb 2026Torridge8.1
Hillsmoor Solar Farmsolar farmsolar farm1.2operationalupdated Aug 2017Jun 2014granted Oct 2014Aug 2017West Devon9.4
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Woodterrill Farmsolar farmsolar farm0.2approved, not built may be out of dateupdated Nov 2022Sep 2022granted Oct 2022Nov 2022Torridge3.4
Deptford Farm, Ebberley Hillbattery storagebattery storage—approved, not builtupdated Feb 2026Dec 2023refused Jul 2024Feb 2026Torridge8.1
Hatchmoor Industrial Estate, Hatherleigh Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Nov 2025Jan 2025refused Apr 2025Nov 2025West Devon8.6

Distance from the average position of the EX19 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm6033078
Battery storage202000.2

MW in pipeline: pending, approved and under-construction capacity.

How Torridge decides solar, wind and battery applications

ApplicationsTorridgeUK
Decided applications (solar, wind, battery)4510,236
Refused12 (27%)19%
Solar refused4 of 3112%
Onshore wind refused6 of 845%
Battery storage refused2 of 616%
Median time from submission to decision24.1 weeks17.0 weeks
Appeals lodged / allowed3 / 7—

All projects in Torridge

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near EX19, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.