Energy Projects Near You

Solar, wind and battery projects near South Molton (EX36)

8 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of EX36 (North Devon): 2 approved but not yet running, 3 operational. The largest live scheme is West Buckland School, West Buckland (0.4 MW solar farm, approved on 14 June 2023, not yet built), 9.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8projects within 10 km
0awaiting a decision
2approved, not running
3operational

Projects within 10 km of EX36

Projects of 1 MW and more (6)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Hacche Barton Solar Farmsolar farmsolar farm9.2application withdrawnupdated Jul 2013Jul 2012—Jul 2013North Devon3.4
Kingsland Barton Solar Farmsolar farmsolar farm5operationalupdated Dec 2014Jun 2013granted Oct 2013Dec 2014North Devon4.7
Three Moors Wind Farmwind farmwind farm22refused on appealupdated Dec 2010Nov 2007refused Sep 2008Dec 2010North Devon5.5
Cross Moorwind farmwind farm4refusedupdated Jun 2012Dec 2006refused Mar 2012Jun 2012North Devon7.3
Bommertown Solar Farmsolar farmsolar farm5operationalupdated Jul 2016Jul 2012granted Aug 2014Jul 2016North Devon7.9
Batsworthy Crosswind farmwind farm18operationalupdated Nov 2016Nov 2006granted Oct 2012Nov 2016North Devon9.1
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Bucknell Way, Hacche Lane -Battery Energy Storagebattery storagebattery storage0.2approved, not builtupdated Jan 2025Aug 2024granted Dec 2024Jan 2025North Devon3.1
West Buckland School, West Bucklandsolar farmsolar farm0.4approved, not builtupdated Jun 2023Feb 2023granted Jun 2023Jun 2023North Devon9.3

Distance from the average position of the EX36 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm401200.4
Wind farm300120
Battery storage101000.2

MW in pipeline: pending, approved and under-construction capacity.

How North Devon decides solar, wind and battery applications

ApplicationsNorth DevonUK
Decided applications (solar, wind, battery)3710,236
Refused9 (24%)19%
Solar refused4 of 2612%
Onshore wind refused5 of 645%
Battery storage refused0 of 516%
Median time from submission to decision23.3 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

All projects in North Devon

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.