Batsworthy Cross (18 MW wind farm)

Batsworthy Cross is an 18 MW wind farm project in North Devon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 7 April 2016; the record was last updated on 30 November 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18 MWwind farm
operationalstatus in REPD
30 November 2016record last updated
North Devoncouncil area

Planning timeline

DateStage
18 November 2006Application submitted
20 July 2011Refused by the planning authority
22 October 2012Planning permission granted
22 October 2012Appeal allowed
18 January 2016Construction started
7 April 2016Operational

Project details

Technology
wind farm
Capacity
18 MW
Status (REPD)
operational
Record last updated
30 November 2016
Operator or applicant
Blackrock Real Assets
Planning authority
North Devon
Planning application reference
43272
Appeal reference
A/11/2162070/NWF
Turbines
9
Turbine height
103 m
Address (REPD)
Batsworthy Cross , Creacombe , North Devon
Council area (by location)
North Devon
Time to decision
309 weeks
REPD reference
4057

Who decides

ApplicationsNorth DevonUK
Decided applications (solar, wind, battery)3710,236
Refused9 (24%)19%
Solar refused4 of 2612%
Onshore wind refused5 of 645%
Battery storage refused0 of 516%
Median time from submission to decision23.3 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Three Moors Wind Farmwind farm22refused on appeal3.9
Bickham Moor Wind Farmwind farm12refused on appeal5.1
Bommertown Solar Farmsolar farm5operational5.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.9717, -3.6891).