Bickham Moor Wind Farm (12 MW)
Bickham Moor Wind Farm is a 12 MW wind farm project in North Devon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 29 January 2010; the record was last updated on 15 May 2011.
12 MWwind farm
refused on appealstatus in REPD
15 May 2011record last updated
North Devoncouncil area
Planning timeline
| Date | Stage |
|---|---|
| 22 November 2007 | Application submitted |
| 9 September 2008 | Appeal lodged |
| 29 January 2010 | Refused by the planning authority |
| 29 January 2010 | Appeal refused |
Project details
- Technology
- wind farm
- Capacity
- 12 MW
- Status (REPD)
- refused on appeal
- Record last updated
- 15 May 2011
- Operator or applicant
- Coronation Power Limited
- Planning authority
- Mid Devon
- Planning application reference
- 07/02262/MFUL
- Appeal reference
- APP/Y1138/A/08/2084526
- Turbines
- 4
- Address (REPD)
- Near Oakford, Mid Devon
- Council area (by location)
- North Devon
- Time to decision
- 114 weeks
- REPD reference
- 3051
Who decides
| Applications | Mid Devon | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 39 | 10,236 |
| Refused | 13 (33%) | 19% |
| Solar refused | 11 of 34 | 12% |
| Onshore wind refused | 1 of 1 | 45% |
| Battery storage refused | 1 of 4 | 16% |
| Median time from submission to decision | 13.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 8 / 5 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Batsworthy Cross | wind farm | 18 | operational | 5.1 |
| Bommertown Solar Farm | solar farm | 5 | operational | 6.2 |
| Three Moors Wind Farm | wind farm | 22 | refused on appeal | 7.7 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.9818, -3.618).