Energy Projects Near You

Bommertown Solar Farm (5 MW)

Bommertown Solar Farm is a 5 MW solar farm project in North Devon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 16 December 2015; the record was last updated on 28 July 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
28 July 2016record last updated
North Devoncouncil area

Planning timeline

DateStage
30 July 2012Application submitted
23 October 2013Refused by the planning authority
5 August 2014Planning permission granted
5 August 2014Appeal allowed
16 December 2015Operational
6 February 2016Construction started

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
28 July 2016
Operator or applicant
Steadfast Molland Solar Ltd
Planning authority
North Devon
Planning application reference
54402
Appeal reference
APP/X1118/A/14/2211328
Site area
12.3 ha
Address (REPD)
Bommertown Farm, Bottreaux Mill, South Molton
Council area (by location)
North Devon
Time to decision
105 weeks
REPD reference
2101

Who decides

ApplicationsNorth DevonUK
Decided applications (solar, wind, battery)3710,236
Refused9 (24%)19%
Solar refused4 of 2612%
Onshore wind refused5 of 645%
Battery storage refused0 of 516%
Median time from submission to decision23.3 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Three Moors Wind Farmwind farm22refused on appeal3.6
Batsworthy Crosswind farm18operational5.3
Bickham Moor Wind Farmwind farm12refused on appeal6.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.0189, -3.6846).