Energy Projects Near You

Three Moors Wind Farm (22 MW)

Three Moors Wind Farm is a 22 MW wind farm project in North Devon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 29 January 2009; the record was last updated on 6 December 2010.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

22 MWwind farm
refused on appealstatus in REPD
6 December 2010record last updated
North Devoncouncil area

Planning timeline

DateStage
6 November 2007Application submitted
4 September 2008Refused by the planning authority
29 January 2009Appeal refused

Project details

Technology
wind farm
Capacity
22 MW
Status (REPD)
refused on appeal
Record last updated
6 December 2010
Operator or applicant
Airtricity Developments (UK) Limited
Planning authority
North Devon
Planning application reference
45489
Turbines
9
Address (REPD)
Paul's Moor, Wester Bullarford, West Moor North of Knowstone South Molton EX364QH
Council area (by location)
North Devon
Time to decision
43 weeks
REPD reference
3443

Who decides

ApplicationsNorth DevonUK
Decided applications (solar, wind, battery)3710,236
Refused9 (24%)19%
Solar refused4 of 2612%
Onshore wind refused5 of 645%
Battery storage refused0 of 516%
Median time from submission to decision23.3 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bommertown Solar Farmsolar farm5operational3.6
Batsworthy Crosswind farm18operational3.9
Bickham Moor Wind Farmwind farm12refused on appeal7.7
Hacche Barton Solar Farmsolar farm9.2application withdrawn8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.9986, -3.7251).