Three Moors Wind Farm (22 MW)
Three Moors Wind Farm is a 22 MW wind farm project in North Devon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 29 January 2009; the record was last updated on 6 December 2010.
22 MWwind farm
refused on appealstatus in REPD
6 December 2010record last updated
North Devoncouncil area
Planning timeline
| Date | Stage |
|---|---|
| 6 November 2007 | Application submitted |
| 4 September 2008 | Refused by the planning authority |
| 29 January 2009 | Appeal refused |
Project details
- Technology
- wind farm
- Capacity
- 22 MW
- Status (REPD)
- refused on appeal
- Record last updated
- 6 December 2010
- Operator or applicant
- Airtricity Developments (UK) Limited
- Planning authority
- North Devon
- Planning application reference
- 45489
- Turbines
- 9
- Address (REPD)
- Paul's Moor, Wester Bullarford, West Moor North of Knowstone South Molton EX364QH
- Council area (by location)
- North Devon
- Time to decision
- 43 weeks
- REPD reference
- 3443
Who decides
| Applications | North Devon | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 37 | 10,236 |
| Refused | 9 (24%) | 19% |
| Solar refused | 4 of 26 | 12% |
| Onshore wind refused | 5 of 6 | 45% |
| Battery storage refused | 0 of 5 | 16% |
| Median time from submission to decision | 23.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 3 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Bommertown Solar Farm | solar farm | 5 | operational | 3.6 |
| Batsworthy Cross | wind farm | 18 | operational | 3.9 |
| Bickham Moor Wind Farm | wind farm | 12 | refused on appeal | 7.7 |
| Hacche Barton Solar Farm | solar farm | 9.2 | application withdrawn | 8.8 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.9986, -3.7251).