Solar, wind and battery projects near Barnstaple (EX32)
24 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of EX32 (North Devon): 3 are waiting for a planning decision, 8 approved but not yet running, 8 operational. The largest live scheme is Bulworthy Farm, Stoney Cross (50 MW battery storage, application submitted on 30 July 2025, no decision recorded), 9.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of EX32
Projects of 1 MW and more (16)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Petroc, Sticklepathbattery storage | battery storage | 1 | application submittedupdated Oct 2024 | Aug 2024 | — | Oct 2024 | North Devon | 3.5 |
| HOLLAMOOR FARM (wind)wind farm | wind farm | 1.5 | application withdrawnupdated Sep 2014 | Jun 2014 | — | Sep 2014 | North Devon | 4.3 |
| Hollamoor Farm (PV)solar farm | solar farm | 2 | operationalupdated Feb 2014 | Nov 2012 | granted Feb 2013 | Feb 2014 | North Devon | 4.5 |
| Hollamoor Farmsolar farm | solar farm | 2.5 | abandonedupdated Sep 2018 | Sep 2015 | granted Mar 2016 | Sep 2018 | North Devon | 4.5 |
| Philip Dennis Food Servicebattery storage | battery storage | 3.8 | operationalupdated Mar 2019 | Oct 2017 | granted Dec 2017 | Mar 2019 | North Devon | 4.8 |
| Horsacott Farm Solar Parksolar farm | solar farm | 6.4 | operationalupdated Mar 2014 | Jul 2012 | granted Nov 2012 | Mar 2014 | North Devon | 6.3 |
| Collacott Farmsolar farm | solar farm | 4.5 | operationalupdated Apr 2016 | Jan 2015 | granted Jun 2015 | Apr 2016 | North Devon | 7.6 |
| Litchardon Cross Solar Farmsolar farm | solar farm | 49.9 | operationalupdated Feb 2024 | Jul 2020 | granted May 2021 | Feb 2024 | North Devon | 7.7 |
| Luscott Bartonsolar farm | solar farm | 13 | operationalupdated Feb 2016 | Aug 2014 | granted Sep 2015 | Feb 2016 | North Devon | 8.2 |
| Bratton Fleming Solar Farmsolar farm | solar farm | 5 | operationalupdated Apr 2013 | Feb 2011 | granted Apr 2012 | Apr 2013 | North Devon | 8.9 |
| The Old Racecoursewind farm | wind farm | 2.2 | refusedupdated Mar 2003 | Aug 2000 | refused Dec 2001 | Mar 2003 | North Devon | 9.4 |
| Buttercombe Lane Solar Farmsolar farm | solar farm | 15 | approved, not builtupdated May 2026 | Jun 2025 | granted Mar 2026 | May 2026 | North Devon | 9.6 |
| Perrigo, Exeter Roadsolar farm | solar farm | 5.9 | approved, not built may be out of dateupdated Jul 2023 | Dec 2022 | granted Jun 2023 | Jul 2023 | North Devon | 9.7 |
| Bulworthy Farm, Stoney Crossbattery storage | battery storage | 50 | application submittedupdated Sep 2025 | Jul 2025 | — | Sep 2025 | Torridge | 9.8 |
| Bulworthy Farm, Stoney Crosssolar farm | solar farm | 49.9 | application submittedupdated Sep 2025 | Jul 2025 | — | Sep 2025 | Torridge | 9.8 |
| Fullabrook Farm Wind Turbinewind turbine | wind turbine | 2 | application withdrawnupdated Sep 2014 | Jul 2014 | — | Sep 2014 | North Devon | 9.9 |
Smaller schemes under 1 MW, mostly rooftop solar (8)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| St Georges Road Energy Storage Facilitybattery storage | battery storage | 0.2 | application withdrawnupdated Oct 2024 | Aug 2024 | — | Oct 2024 | North Devon | 2.8 |
| Petroc, Old Sticklepath Hillrooftop solar | rooftop solar | 0.8 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Sep 2023 | Sep 2023 | North Devon | 3.5 |
| Greenacres, Roundswell - Micro Energy Storage Projectbattery storage | battery storage | 0.2 | approved, not builtupdated Feb 2025 | Jan 2025 | granted Feb 2025 | Feb 2025 | North Devon | 4.6 |
| Fishleigh Road, Roundswell Business Parkbattery storage | battery storage | 0.2 | approved, not builtupdated Feb 2025 | Jan 2025 | granted Feb 2025 | Feb 2025 | North Devon | 4.9 |
| West Buckland School, West Bucklandsolar farm | solar farm | 0.4 | approved, not builtupdated Jun 2023 | Feb 2023 | granted Jun 2023 | Jun 2023 | North Devon | 8.2 |
| Horwoodsolar farm | solar farm | — | approved, not built may be out of dateupdated Apr 2022 | Mar 2022 | granted May 2022 | Apr 2022 | North Devon | 9.7 |
| Exeter Road, Brauntonsolar farm | solar farm | 0.8 | under constructionupdated Jan 2022 | Dec 2021 | granted May 2022 | Jan 2022 | North Devon | 9.7 |
| Perrigo,Wraftonrooftop solar | rooftop solar | 0.5 | operationalupdated Jan 2022 | Sep 2021 | granted Nov 2021 | Jan 2022 | North Devon | 9.7 |
Distance from the average position of the EX32 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 13 | 1 | 5 | 6 | 0 | 72 |
| Rooftop solar | 2 | 0 | 1 | 1 | 0 | 0.8 |
| Wind farm | 2 | 0 | 0 | 0 | 1 | 0 |
| Wind turbine | 1 | 0 | 0 | 0 | 0 | 0 |
| Battery storage | 6 | 2 | 2 | 1 | 0 | 51.4 |
MW in pipeline: pending, approved and under-construction capacity.
How North Devon decides solar, wind and battery applications
| Applications | North Devon | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 37 | 10,236 |
| Refused | 9 (24%) | 19% |
| Solar refused | 4 of 26 | 12% |
| Onshore wind refused | 5 of 6 | 45% |
| Battery storage refused | 0 of 5 | 16% |
| Median time from submission to decision | 23.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 3 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near EX32, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.