Energy Projects Near You

Perrigo, Exeter Road (5.9 MW solar farm)

Perrigo, Exeter Road is a 5.9 MW solar farm project in North Devon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 20 June 2023, not yet built; the record was last updated on 13 July 2023. REPD also records that the planning permission expired on 20 June 2026, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5.9 MWsolar farm
approved, not builtmay be out of datestatus in REPD
13 July 2023record last updated
North Devoncouncil area

REPD also records that the planning permission expired on 20 June 2026, so the project may not go ahead in this form.

Planning timeline

DateStage
23 December 2022Application submitted
20 June 2023Planning permission granted
20 June 2026Permission expired

Project details

Technology
solar farm
Capacity
5.9 MW
Status (REPD)
approved, not built
Record last updated
13 July 2023
Operator or applicant
Wrafton Laboratories (Trading as Perrigo)
Planning authority
North Devon
Planning application reference
76423
Site area
7.8 ha
Address (REPD)
Perrigo Exeter Road Braunton
Council area (by location)
North Devon
Time to decision
26 weeks
Name in REPD
Perrigo, Exeter Road - Solar Panels
REPD reference
13053

Who decides

ApplicationsNorth DevonUK
Decided applications (solar, wind, battery)3710,236
Refused9 (24%)19%
Solar refused4 of 2612%
Onshore wind refused5 of 645%
Battery storage refused0 of 516%
Median time from submission to decision23.3 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Buttercombe Lane Solar Farmsolar farm15approved, not built2.6
Luscott Bartonsolar farm13operational2.7
Horsacott Farm Solar Parksolar farm6.4operational4.8
West Hill Farm (solar)solar farm7.3operational5.6
Litchardon Cross Solar Farmsolar farm49.9operational6.2
Barton Close Farmsolar farm5.5operational6.5
Fullabrook Down Wind Farmwind farm66operational7.5
West Webbery Farm, The Waterbattery storage99.4application submitted9.3
Bulworthy Farm, Stoney Crosssolar farm49.9application submitted9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.097, -4.1529).