Fullabrook Down Wind Farm (66 MW)
Fullabrook Down Wind Farm is a 66 MW wind farm project in North Devon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 24 January 2012; the record was last updated on 19 April 2013.
66 MWwind farm
operationalstatus in REPD
19 April 2013record last updated
North Devoncouncil area
Planning timeline
| Date | Stage |
|---|---|
| 18 October 2004 | Application submitted |
| 10 October 2007 | Planning permission granted |
| 1 July 2008 | Construction started |
| 24 January 2012 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 66 MW
- Status (REPD)
- operational
- Record last updated
- 19 April 2013
- Operator or applicant
- Devon Wind Power Ltd
- Planning authority
- North Devon
- Planning application reference
- 38622
- Turbines
- 22
- Address (REPD)
- Fullabrook Down, Crackaway, Barton
- Council area (by location)
- North Devon
- Time to decision
- 155 weeks
- REPD reference
- 4033
Who decides
| Applications | North Devon | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 37 | 10,236 |
| Refused | 9 (24%) | 19% |
| Solar refused | 4 of 26 | 12% |
| Onshore wind refused | 5 of 6 | 45% |
| Battery storage refused | 0 of 5 | 16% |
| Median time from submission to decision | 23.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 3 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Great Shelfin Farm | wind farm | 6.9 | application withdrawn | 2.7 |
| West Hill Farm (solar) | solar farm | 7.3 | operational | 2.7 |
| Buttercombe Lane Solar Farm | solar farm | 15 | approved, not built | 4.9 |
| Barton Close Farm | solar farm | 5.5 | operational | 5.0 |
| Luscott Barton | solar farm | 13 | operational | 5.3 |
| Perrigo, Exeter Road | solar farm | 5.9 | approved, not built | 7.5 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1569, -4.1027).