West Hill Farm (solar) (7.3 MW)

West Hill Farm (solar) is a 7.3 MW solar farm project in North Devon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 29 July 2014; the record was last updated on 3 February 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.3 MWsolar farm
operationalstatus in REPD
3 February 2015record last updated
North Devoncouncil area

Planning timeline

DateStage
6 August 2012Application submitted
30 November 2012Planning permission granted
29 July 2014Operational

Project details

Technology
solar farm
Capacity
7.3 MW
Status (REPD)
operational
Record last updated
3 February 2015
Operator or applicant
Lumicity
Planning authority
North Devon
Planning application reference
54388
Address (REPD)
ILFRACOMBE DEVON
Council area (by location)
North Devon
Time to decision
17 weeks
REPD reference
1828

Who decides

ApplicationsNorth DevonUK
Decided applications (solar, wind, battery)3710,236
Refused9 (24%)19%
Solar refused4 of 2612%
Onshore wind refused5 of 645%
Battery storage refused0 of 516%
Median time from submission to decision23.3 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Barton Close Farmsolar farm5.5operational2.7
Fullabrook Down Wind Farmwind farm66operational2.7
Buttercombe Lane Solar Farmsolar farm15approved, not built3.2
Great Shelfin Farmwind farm6.9application withdrawn4.0
Luscott Bartonsolar farm13operational4.1
Perrigo, Exeter Roadsolar farm5.9approved, not built5.6
Horsacott Farm Solar Parksolar farm6.4operational9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1461, -4.1377).