Energy Projects Near You

Buttercombe Lane Solar Farm (15 MW)

Buttercombe Lane Solar Farm is a 15 MW solar farm project in North Devon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 26 March 2026, not yet built; the record was last updated on 19 May 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWsolar farm
approved, not builtstatus in REPD
19 May 2026record last updated
North Devoncouncil area

Planning timeline

DateStage
4 June 2025Application submitted
26 March 2026Planning permission granted
26 March 2031Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
15 MW
Status (REPD)
approved, not built
Record last updated
19 May 2026
Operator or applicant
Exagen Development Limited
Planning authority
North Devon
Planning application reference
80182
Site area
44.1 ha
Address (REPD)
S/O Buttercombe Lane, Braunton
Council area (by location)
North Devon
Time to decision
42 weeks
Name in REPD
Buttercombe Lane - Solar Farm
REPD reference
19125

Who decides

ApplicationsNorth DevonUK
Decided applications (solar, wind, battery)3710,236
Refused9 (24%)19%
Solar refused4 of 2612%
Onshore wind refused5 of 645%
Battery storage refused0 of 516%
Median time from submission to decision23.3 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Luscott Bartonsolar farm13operational1.3
Perrigo, Exeter Roadsolar farm5.9approved, not built2.6
West Hill Farm (solar)solar farm7.3operational3.2
Barton Close Farmsolar farm5.5operational4.8
Fullabrook Down Wind Farmwind farm66operational4.9
Horsacott Farm Solar Parksolar farm6.4operational6.2
Great Shelfin Farmwind farm6.9application withdrawn7.0
Litchardon Cross Solar Farmsolar farm49.9operational8.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1177, -4.1359).