Litchardon Cross Solar Farm (49.9 MW)

Litchardon Cross Solar Farm is a 49.9 MW solar farm project in North Devon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational; the record was last updated on 28 February 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
operationalstatus in REPD
28 February 2024record last updated
North Devoncouncil area

Planning timeline

DateStage
24 July 2020Application submitted
14 May 2021Planning permission granted
1 September 2022Construction started

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
operational
Record last updated
28 February 2024
Operator or applicant
Aura Power / Infinis Energy Services
Planning authority
North Devon
Planning application reference
71708
Site area
36.6 ha
Address (REPD)
Land at Litchardon Cross, Road From Litchardon Cross, Newton Tracey, To Voscombe Cross, Barnstaple, Devon
Council area (by location)
North Devon
Time to decision
42 weeks
Contracts for Difference
AR4
REPD reference
8101

Who decides

ApplicationsNorth DevonUK
Decided applications (solar, wind, battery)3710,236
Refused9 (24%)19%
Solar refused4 of 2612%
Onshore wind refused5 of 645%
Battery storage refused0 of 516%
Median time from submission to decision23.3 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Horsacott Farm Solar Parksolar farm6.4operational2.3
Bulworthy Farm, Stoney Crosssolar farm49.9application submitted3.5
West Webbery Farm, The Waterbattery storage99.4application submitted4.2
North Devon Wind Farmwind farm7.5refused4.5
Gammaton Moor Solar farmsolar farm32operational4.5
Gammaton Barton Farm, Alverdiscottbattery storage100approved, not built4.9
Perrigo, Exeter Roadsolar farm5.9approved, not built6.2
Luscott Bartonsolar farm13operational7.3
Buttercombe Lane Solar Farmsolar farm15approved, not built8.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.0452, -4.121).