Gammaton Moor Solar farm (32 MW)

Gammaton Moor Solar farm is a 32 MW solar farm project in Torridge, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 April 2026; the record was last updated on 8 June 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

32 MWsolar farm
operationalstatus in REPD
8 June 2026record last updated
Torridgecouncil area

Planning timeline

DateStage
1 September 2021Application submitted
19 April 2022Planning permission granted
1 April 2026Operational

Project details

Technology
solar farm
Capacity
32 MW
Status (REPD)
operational
Record last updated
8 June 2026
Operator or applicant
Sonnedix
Planning authority
Torridge
Planning application reference
1/1057/2021/FULM
Site area
63.3 ha
Address (REPD)
Webbery Barton & Cleave Farm
Council area (by location)
Torridge
Time to decision
33 weeks
Contracts for Difference
AR5
REPD reference
9785

Who decides

ApplicationsTorridgeUK
Decided applications (solar, wind, battery)4510,236
Refused12 (27%)19%
Solar refused4 of 3112%
Onshore wind refused6 of 845%
Battery storage refused2 of 616%
Median time from submission to decision24.1 weeks17.0 weeks
Appeals lodged / allowed3 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
North Devon Wind Farmwind farm7.5refused1.0
West Webbery Farm, The Waterbattery storage99.4application submitted1.1
Gammaton Barton Farm, Alverdiscottbattery storage100approved, not built1.3
Bulworthy Farm, Stoney Crosssolar farm49.9application submitted1.4
Litchardon Cross Solar Farmsolar farm49.9operational4.5
Horsacott Farm Solar Parksolar farm6.4operational6.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.0063, -4.1411).