North Devon Wind Farm (7.5 MW)
North Devon Wind Farm is a 7.5 MW wind farm project in Torridge, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 2 February 2015; the record was last updated on 9 February 2015.
7.5 MWwind farm
refusedstatus in REPD
9 February 2015record last updated
Torridgecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 8 April 2013 | Application submitted |
| 2 February 2015 | Refused by the planning authority |
Project details
- Technology
- wind farm
- Capacity
- 7.5 MW
- Status (REPD)
- refused
- Record last updated
- 9 February 2015
- Operator or applicant
- North Devon Wind Energy Ltd
- Planning authority
- Torridge
- Planning application reference
- 1/0288/2013/FULM
- Turbines
- 3
- Address (REPD)
- Land To East Of Alverdiscott Substation Webbery Bideford Devon EX39 4PU
- Council area (by location)
- Torridge
- Time to decision
- 95 weeks
- REPD reference
- 4302
Who decides
| Applications | Torridge | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 45 | 10,236 |
| Refused | 12 (27%) | 19% |
| Solar refused | 4 of 31 | 12% |
| Onshore wind refused | 6 of 8 | 45% |
| Battery storage refused | 2 of 6 | 16% |
| Median time from submission to decision | 24.1 weeks | 17.0 weeks |
| Appeals lodged / allowed | 3 / 7 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Gammaton Moor Solar farm | solar farm | 32 | operational | 1.0 |
| Bulworthy Farm, Stoney Cross | solar farm | 49.9 | application submitted | 1.1 |
| West Webbery Farm, The Water | battery storage | 99.4 | application submitted | 2.0 |
| Gammaton Barton Farm, Alverdiscott | battery storage | 100 | approved, not built | 2.2 |
| Litchardon Cross Solar Farm | solar farm | 49.9 | operational | 4.5 |
| Horsacott Farm Solar Park | solar farm | 6.4 | operational | 6.7 |
| Deptford Farm, Ebberley Hill Solar Farm | solar farm | 27.8 | approved, not built | 9.8 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.0046, -4.1278).