Barton Close Farm (5.5 MW solar farm)

Barton Close Farm is a 5.5 MW solar farm project in North Devon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 February 2016; the record was last updated on 14 April 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5.5 MWsolar farm
operationalstatus in REPD
14 April 2016record last updated
North Devoncouncil area

Planning timeline

DateStage
4 October 2012Application submitted
18 March 2013Refused by the planning authority
15 April 2014Planning permission granted
15 April 2014Appeal allowed
10 June 2015Construction started
15 February 2016Operational

Project details

Technology
solar farm
Capacity
5.5 MW
Status (REPD)
operational
Record last updated
14 April 2016
Operator or applicant
British Solar Renewables
Planning authority
North Devon
Planning application reference
54722
Appeal reference
A/13/2199207/NWF
Address (REPD)
Georgeham, Braunton, Devon
Council area (by location)
North Devon
Time to decision
80 weeks
REPD reference
1864

Who decides

ApplicationsNorth DevonUK
Decided applications (solar, wind, battery)3710,236
Refused9 (24%)19%
Solar refused4 of 2612%
Onshore wind refused5 of 645%
Battery storage refused0 of 516%
Median time from submission to decision23.3 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
West Hill Farm (solar)solar farm7.3operational2.7
Buttercombe Lane Solar Farmsolar farm15approved, not built4.8
Great Shelfin Farmwind farm6.9application withdrawn5.0
Fullabrook Down Wind Farmwind farm66operational5.0
Luscott Bartonsolar farm13operational6.1
Perrigo, Exeter Roadsolar farm5.9approved, not built6.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1539, -4.174).