Bratton Fleming Solar Farm (5 MW)

Bratton Fleming Solar Farm is a 5 MW solar farm project in North Devon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 21 March 2013; the record was last updated on 12 April 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
12 April 2013record last updated
North Devoncouncil area

Planning timeline

DateStage
1 February 2011Application submitted
17 April 2012Planning permission granted
3 December 2012Construction started
21 March 2013Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
12 April 2013
Operator or applicant
Wessex Solar Energy
Planning authority
North Devon
Planning application reference
51698
Address (REPD)
Land adjacent to four cross way, Bratton Fleming
Council area (by location)
North Devon
Time to decision
63 weeks
REPD reference
1557

Who decides

ApplicationsNorth DevonUK
Decided applications (solar, wind, battery)3710,236
Refused9 (24%)19%
Solar refused4 of 2612%
Onshore wind refused5 of 645%
Battery storage refused0 of 516%
Median time from submission to decision23.3 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Capeland Farmsolar farm8.3operational1.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1252, -3.9249).