Capeland Farm (8.3 MW solar farm)

Capeland Farm is an 8.3 MW solar farm project in North Devon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 27 February 2015; the record was last updated on 16 June 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8.3 MWsolar farm
operationalstatus in REPD
16 June 2015record last updated
North Devoncouncil area

Planning timeline

DateStage
19 June 2013Application submitted
28 February 2014Planning permission granted
1 September 2014Construction started
27 February 2015Operational

Project details

Technology
solar farm
Capacity
8.3 MW
Status (REPD)
operational
Record last updated
16 June 2015
Operator or applicant
juwi Renewable Energies
Planning authority
North Devon
Planning application reference
55798
Site area
22.4 ha
Address (REPD)
Capelands Farm, Bratton Fleming, Barnstaple, Devon
Council area (by location)
North Devon
Time to decision
36 weeks
REPD reference
1943

Who decides

ApplicationsNorth DevonUK
Decided applications (solar, wind, battery)3710,236
Refused9 (24%)19%
Solar refused4 of 2612%
Onshore wind refused5 of 645%
Battery storage refused0 of 516%
Median time from submission to decision23.3 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bratton Fleming Solar Farmsolar farm5operational1.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1312, -3.9082).