Coldharbour Farm, Ashreigney (50 MW solar farm)

Coldharbour Farm, Ashreigney is a 50 MW solar farm project in Torridge, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 19 September 2023, not yet built; the record was last updated on 17 June 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWsolar farm
approved, not builtstatus in REPD
17 June 2026record last updated
Torridgecouncil area

Planning timeline

DateStage
14 July 2021Application submitted
19 September 2023Planning permission granted
19 September 2026Permission expired

Project details

Technology
solar farm
Capacity
50 MW
Status (REPD)
approved, not built
Record last updated
17 June 2026
Operator or applicant
Coldharbour Solar Park Limited
Planning authority
Torridge
Planning application reference
1/0823/2021/FULM
Site area
59.6 ha
Address (REPD)
Coldharbour Farm Ashreigney Chulmleigh
Council area (by location)
Torridge
Time to decision
114 weeks
Contracts for Difference
AR6
Name in REPD
Coldharbour Farm, Ashreigney - Solar Photovoltaic Array
REPD reference
9456

Who decides

ApplicationsTorridgeUK
Decided applications (solar, wind, battery)4510,236
Refused12 (27%)19%
Solar refused4 of 3112%
Onshore wind refused6 of 845%
Battery storage refused2 of 616%
Median time from submission to decision24.1 weeks17.0 weeks
Appeals lodged / allowed3 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Beaford Brook Solar Parksolar farm5.2operational4.7
Deptford Farm, Ebberley Hill Solar Farmsolar farm27.8approved, not built6.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.8971, -3.9839).