Solar, wind and battery projects near Crediton (EX17)

7 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of EX17 (Mid Devon): 3 approved but not yet running, 3 operational. The largest live scheme is George Hil, Avranches Avenue - Micro Energy Storage Facility (0.2 MW battery storage, approved on 15 February 2024, not yet built), 3.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7projects within 10 km
0awaiting a decision
3approved, not running
3operational

Projects within 10 km of EX17

Projects of 1 MW and more (4)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Dunscombe Solarsolar farmsolar farm5refused on appealupdated Sep 2016Aug 2015refused Dec 2015Sep 2016Mid Devon4.0
Broadgate Solar Farmsolar farmsolar farm1.1operationalupdated Oct 2013Mar 2012granted May 2012Oct 2013Mid Devon5.1
Sharland Solar Farmsolar farmsolar farm2.8operationalupdated May 2017Mar 2015granted Jul 2015May 2017Mid Devon5.1
Ellicombe Farmsolar farmsolar farm1.4operationalupdated Apr 2013Sep 2012granted Dec 2012Apr 2013Mid Devon5.9
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
George Hil, Avranches Avenue - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Mar 2024Dec 2023granted Feb 2024Mar 2024Mid Devon3.1
Lords Meadow Leisure Centrerooftop solarrooftop solar—approved, not built may be out of dateupdated Dec 2022Sep 2022granted Nov 2022Dec 2022Mid Devon4.9
Clannaborough Barton, Bowrooftop solarrooftop solar0.2approved, not builtupdated Apr 2025Feb 2025granted Mar 2025Apr 2025Mid Devon5.2

Distance from the average position of the EX17 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm400310
Rooftop solar202000.2
Battery storage101000.2

MW in pipeline: pending, approved and under-construction capacity.

How Mid Devon decides solar, wind and battery applications

ApplicationsMid DevonUK
Decided applications (solar, wind, battery)3910,236
Refused13 (33%)19%
Solar refused11 of 3412%
Onshore wind refused1 of 145%
Battery storage refused1 of 416%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed8 / 5—

All projects in Mid Devon

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near EX17, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.