Dunscombe Solar (5 MW)

Dunscombe Solar is a 5 MW solar farm project in Mid Devon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 2 August 2016; the record was last updated on 1 September 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
refused on appealstatus in REPD
1 September 2016record last updated
Mid Devoncouncil area

Planning timeline

DateStage
7 August 2015Application submitted
11 December 2015Refused by the planning authority
26 April 2016Appeal lodged
2 August 2016Appeal refused

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
refused on appeal
Record last updated
1 September 2016
Operator or applicant
Elgin Energy
Planning authority
Mid Devon
Planning application reference
15/01194/MFUL
Appeal reference
APP/Y1138/W/16/3147127
Site area
13.8 ha
Address (REPD)
Land a Dunscombe, Cheriton Fitzpaine, Crediton, Newton St Cyres
Council area (by location)
Mid Devon
Time to decision
18 weeks
REPD reference
5573

Who decides

ApplicationsMid DevonUK
Decided applications (solar, wind, battery)3910,236
Refused13 (33%)19%
Solar refused11 of 3412%
Onshore wind refused1 of 145%
Battery storage refused1 of 416%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed8 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Goldcross Hillsolar6.9refused8.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.7874, -3.6649).