Energy Projects Near You

Goldcross Hill (6.9 MW solar)

Goldcross Hill is a 6.9 MW solar project in Teignbridge, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 3 December 2012; the record was last updated on 7 February 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.9 MWsolar
refusedstatus in REPD
7 February 2013record last updated
Teignbridgecouncil area

Planning timeline

DateStage
11 September 2012Application submitted
3 December 2012Refused by the planning authority

Project details

Technology
solar
Capacity
6.9 MW
Status (REPD)
refused
Record last updated
7 February 2013
Operator or applicant
Fulford Solar Park Ltd
Planning authority
Teignbridge
Planning application reference
12/02784/MAJ
Address (REPD)
Land South Of Goldcross Hill, Tedburn St Mary
Council area (by location)
Teignbridge
Time to decision
12 weeks
REPD reference
1071

Earlier applications for this site

ApplicationMWSubmittedOutcome
Goldcross Hill 12/00781/MAJ8.69 March 2012refused 13 July 2012

Who decides

ApplicationsTeignbridgeUK
Decided applications (solar, wind, battery)1410,236
Refused5 (36%)19%
Solar refused4 of 1212%
Battery storage refused1 of 216%
Median time from submission to decision12.4 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Dunscombe Solarsolar farm5refused on appeal8.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.7198, -3.7113).