Galsworthy Wind Park (9.2 MW)

Galsworthy Wind Park is a 9.2 MW wind farm project in Torridge, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 28 November 2014; the record was last updated on 1 December 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.2 MWwind farm
operationalstatus in REPD
1 December 2014record last updated
Torridgecouncil area

Planning timeline

DateStage
4 April 2008Application submitted
11 September 2008Planning permission granted
1 May 2011Construction started
28 November 2014Operational

Project details

Technology
wind farm
Capacity
9.2 MW
Status (REPD)
operational
Record last updated
1 December 2014
Operator or applicant
Ecotricity
Planning authority
Torridge
Planning application reference
1/0375/2008/FUL
Turbines
4
Address (REPD)
Land At Galsworthy , Buckland Brewer And Bulkworthy
Council area (by location)
Torridge
Time to decision
23 weeks
REPD reference
4624

Who decides

ApplicationsTorridgeUK
Decided applications (solar, wind, battery)4510,236
Refused12 (27%)19%
Solar refused4 of 3112%
Onshore wind refused6 of 845%
Battery storage refused2 of 616%
Median time from submission to decision24.1 weeks17.0 weeks
Appeals lodged / allowed3 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bulkworthy Solar Parksolar farm5approved, not built0.9
Wheelers Crosswind farm7.8refused6.2
Limebury Farm, Horns Cross Solar Farmsolar farm6.5under construction7.6
Walland Farmsolar farm5operational8.3
Chalhanger Farm Solar Parksolar farm6refused on appeal8.8