Energy Projects Near You

Walland Farm (5 MW solar farm)

Walland Farm is a 5 MW solar farm project in Torridge, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 4 February 2015; the record was last updated on 14 May 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
14 May 2015record last updated
Torridgecouncil area

Planning timeline

DateStage
22 May 2014Application submitted
21 August 2014Planning permission granted
11 November 2014Construction started
4 February 2015Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
14 May 2015
Operator or applicant
Lightsource Renewable Energy
Planning authority
Torridge
Planning application reference
1/0518/2014/FULM
Site area
12.2 ha
Address (REPD)
Land Associated With Walland Farm Bucks Cross Woolsery Devon
Council area (by location)
Torridge
Time to decision
13 weeks
REPD reference
2336

Who decides

ApplicationsTorridgeUK
Decided applications (solar, wind, battery)4510,236
Refused12 (27%)19%
Solar refused4 of 3112%
Onshore wind refused6 of 845%
Battery storage refused2 of 616%
Median time from submission to decision24.1 weeks17.0 weeks
Appeals lodged / allowed3 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Limebury Farm, Horns Cross Solar Farmsolar farm6.5under construction1.1
Harbourcross wind farmwind farm10refused7.6
Galsworthy Wind Parkwind farm9.2operational8.3
Wheelers Crosswind farm7.8refused8.5
Bulkworthy Solar Parksolar farm5approved, not built9.0
Trentworthy Solar Farmsolar farm5application withdrawn9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.9758, -4.3468).