Energy Projects Near You

Limebury Farm, Horns Cross Solar Farm (6.5 MW)

Limebury Farm, Horns Cross Solar Farm is a 6.5 MW solar farm project in Torridge, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 October 2024; the record was last updated on 19 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.5 MWsolar farm
under constructionstatus in REPD
19 February 2026record last updated
Torridgecouncil area

Planning timeline

DateStage
28 October 2022Application submitted
10 May 2023Planning permission granted
1 October 2024Construction started

Project details

Technology
solar farm
Capacity
6.5 MW
Status (REPD)
under construction
Record last updated
19 February 2026
Operator or applicant
Green Switch Capital Limited
Planning authority
Torridge
Planning application reference
1/1096/2022/FULM
Site area
10.3 ha
Address (REPD)
Limebury Farm, Horns Cross,
Council area (by location)
Torridge
Time to decision
28 weeks
Contracts for Difference
AR7a
Name in REPD
Limebury Farm, Horns Cross - Solar Farm
REPD reference
12972

Who decides

ApplicationsTorridgeUK
Decided applications (solar, wind, battery)4510,236
Refused12 (27%)19%
Solar refused4 of 3112%
Onshore wind refused6 of 845%
Battery storage refused2 of 616%
Median time from submission to decision24.1 weeks17.0 weeks
Appeals lodged / allowed3 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Walland Farmsolar farm5operational1.1
Galsworthy Wind Parkwind farm9.2operational7.6
Bulkworthy Solar Parksolar farm5approved, not built8.4
Harbourcross wind farmwind farm10refused8.5
Wheelers Crosswind farm7.8refused8.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.9758, -4.3313).