West Venn Solar Farm (5 MW)

West Venn Solar Farm is a 5 MW solar farm project in Torridge, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 13 March 2017; the record was last updated on 31 May 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
31 May 2017record last updated
Torridgecouncil area

Planning timeline

DateStage
3 June 2015Application submitted
1 October 2015Planning permission granted
15 June 2016Construction started
13 March 2017Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
31 May 2017
Operator or applicant
Solar Securities Group
Planning authority
Torridge
Planning application reference
1/0566/2015/FULM
Site area
9.8 ha
Address (REPD)
Land At West Venn Farm, Ashwater, Beaworthy
Council area (by location)
Torridge
Time to decision
17 weeks
REPD reference
5547

Earlier applications for this site

ApplicationMWSubmittedOutcome
West Venn solar farm 1/0368/2013/FULM10.225 April 2013refused 26 November 2013

Who decides

ApplicationsTorridgeUK
Decided applications (solar, wind, battery)4510,236
Refused12 (27%)19%
Solar refused4 of 3112%
Onshore wind refused6 of 845%
Battery storage refused2 of 616%
Median time from submission to decision24.1 weeks17.0 weeks
Appeals lodged / allowed3 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hollow Panson Wind Farmwind farm12application withdrawn4.7
Foxcombe Farm Solar Parksolar farm5operational5.3
Dunsland Cross Wind Farmwind farm7.5operational6.6
Derriton Fields Solar Farmsolar farm11.8operational7.2
East Rightadown Farm, Brandis Corner Solar Farmsolar farm7.6approved, not built7.9
Land At Woodlands Farmsolar farm8refused7.9
West Ditchen Farmsolar farm5operational8.2
CRINACOTT SOLAR FARM (Pyworthy)solar farm6.7operational8.2
Stoneworthybattery storage49.9approved, not built8.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.7544, -4.2994).