Dunsland Cross Wind Farm (7.5 MW)

Dunsland Cross Wind Farm is a 7.5 MW wind farm project in Torridge, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 8 March 2017; the record was last updated on 3 October 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.5 MWwind farm
operationalstatus in REPD
3 October 2017record last updated
Torridgecouncil area

Planning timeline

DateStage
13 January 2012Application submitted
22 January 2013Refused by the planning authority
22 January 2013Planning permission granted
22 January 2013Appeal allowed
29 January 2016Construction started
8 March 2017Operational

Project details

Technology
wind farm
Capacity
7.5 MW
Status (REPD)
operational
Record last updated
3 October 2017
Operator or applicant
Temporis Capital
Planning authority
Torridge
Planning application reference
1/1250/2011/FULM
Appeal reference
13/00008/REF
Turbines
3
Address (REPD)
Land At Dunsland Cross South Of Brandis Corner Holsworthy Devon EX22 7YH
Council area (by location)
Torridge
Time to decision
54 weeks
REPD reference
4227

Who decides

ApplicationsTorridgeUK
Decided applications (solar, wind, battery)4510,236
Refused12 (27%)19%
Solar refused4 of 3112%
Onshore wind refused6 of 845%
Battery storage refused2 of 616%
Median time from submission to decision24.1 weeks17.0 weeks
Appeals lodged / allowed3 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
East Rightadown Farm, Brandis Corner Solar Farmsolar farm7.6approved, not built1.6
Foxcombe Farm Solar Parksolar farm5operational2.5
West Venn Solar Farmsolar farm5operational6.6
Chalhanger Farm Solar Parksolar farm6refused on appeal6.9
Derriton Fields Solar Farmsolar farm11.8operational7.6
Stoneworthybattery storage49.9approved, not built9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.8079, -4.2597).