Energy Projects Near You

Solar, wind and battery projects near Penzance (TR19)

5 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TR19 (Cornwall): 3 approved but not yet running, 1 operational. The largest live scheme is Castle An Dinas Quarry, Ludgvan (0.4 MW solar farm, approved on 25 March 2022, not yet built; REPD status may be out of date), 9.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5projects within 10 km
0awaiting a decision
3approved, not running
1operational

Projects within 10 km of TR19

Projects of 1 MW and more (1)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Land at Boslandew Hillsolar farmsolar farm1refused on appealupdated Feb 2017Jul 2015refused Dec 2015Feb 2017Cornwall6.0
Smaller schemes under 1 MW, mostly rooftop solar (4)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Brew Farm, St Levanwind turbinewind turbine0.2approved, not builtupdated Jun 2026Oct 2025granted Apr 2026Jun 2026Cornwall4.7
Lidl Foodstorerooftop solarrooftop solar0.2operationalupdated Jun 2021Jun 2021granted Aug 2021Jun 2021Cornwall6.5
WM Morrison Supermarkets, Long Rockrooftop solarrooftop solar0.3approved, not builtupdated Dec 2022Oct 2022granted Nov 2022Dec 2022Cornwall9.0
Castle An Dinas Quarry, Ludgvansolar farmsolar farm0.4approved, not built may be out of dateupdated Nov 2021Nov 2021granted Mar 2022Nov 2021Cornwall9.8

Distance from the average position of the TR19 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm201010.4
Rooftop solar201100.3
Wind turbine101000.2

MW in pipeline: pending, approved and under-construction capacity.

How Cornwall decides solar, wind and battery applications

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

All projects in Cornwall

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near TR19, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.