Energy Projects Near You

Solar, wind and battery projects near Marazion (TR17)

14 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TR17 (Cornwall): 10 approved but not yet running, 2 operational. The largest live scheme is Trevarthian Farmhouse Solar PV Farm & Battery Energy Storage (49.9 MW solar farm, approved on 1 June 2026, not yet built), 1.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

14projects within 10 km
0awaiting a decision
10approved, not running
2operational

Projects within 10 km of TR17

Projects of 1 MW and more (5)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Trevarthian Farmhouse Solar PV Farm & Battery Energy Storagesolar farmsolar farm49.9approved, not builtupdated Jun 2026Jun 2025granted Jun 2026Jun 2026Cornwall1.9
Bunkers Hillsolar farmsolar farm5refusedupdated Dec 2015Jun 2015refused Sep 2015Dec 2015Cornwall7.1
Land at Boslandew Hillsolar farmsolar farm1refused on appealupdated Feb 2017Jul 2015refused Dec 2015Feb 2017Cornwall7.4
Wheal Alfred Road Solar Farmsolar farmsolar farm3.5operationalupdated Jul 2013Sep 2012granted Feb 2013Jul 2013Cornwall8.1
Loggans Roundabout, Loggans Road Solar Farmsolar farmsolar farm2.5approved, not builtupdated Mar 2025Apr 2024granted Feb 2025Mar 2025Cornwall9.3
Smaller schemes under 1 MW, mostly rooftop solar (9)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Trevarthian Farmhouse Solar PV Farm & Battery Energy Storagebattery storagebattery storage—approved, not builtupdated Jun 2026Jun 2025granted Jun 2026Jun 2026Cornwall1.9
WM Morrison Supermarkets, Long Rockrooftop solarrooftop solar0.3approved, not builtupdated Dec 2022Oct 2022granted Nov 2022Dec 2022Cornwall3.2
Castle An Dinas Quarry, Ludgvansolar farmsolar farm0.4approved, not built may be out of dateupdated Nov 2021Nov 2021granted Mar 2022Nov 2021Cornwall4.8
Lidl Foodstorerooftop solarrooftop solar0.2operationalupdated Jun 2021Jun 2021granted Aug 2021Jun 2021Cornwall5.5
Riviere Sands Holiday Park, Riviere Towansrooftop solarrooftop solar0.2approved, not builtupdated Feb 2023Dec 2022granted Feb 2023Feb 2023Cornwall8.5
Guildford Road Industrial Estatebattery storagebattery storage0.2approved, not builtupdated Mar 2024Jan 2024granted Mar 2024Mar 2024Cornwall8.8
Penbeagle Industrial Estaterooftop solarrooftop solar0.2approved, not builtupdated Mar 2024Feb 2024granted Feb 2024Mar 2024Cornwall8.8
Tregenna Castle Hotelrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Dec 2022Sep 2022granted Nov 2022Dec 2022Cornwall8.8
Loggans Roundabout, Loggans Roadbattery storagebattery storage—approved, not builtupdated Mar 2025Apr 2024granted Feb 2025Mar 2025Cornwall9.3

Distance from the average position of the TR17 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm6031252.8
Rooftop solar504100.9
Battery storage303000.2

MW in pipeline: pending, approved and under-construction capacity.

How Cornwall decides solar, wind and battery applications

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

All projects in Cornwall

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near TR17, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.