Trevarthian Farmhouse Solar PV Farm & Battery Energy Storage (49.9 MW)

Trevarthian Farmhouse Solar PV Farm & Battery Energy Storage is a 49.9 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 1 June 2026, not yet built; the record was last updated on 17 June 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
17 June 2026record last updated
Cornwallcouncil area

Planning timeline

DateStage
13 June 2025Application submitted
1 June 2026Planning permission granted
1 June 2029Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
17 June 2026
Operator or applicant
Trevarthian Renewables Limited
Planning authority
Cornwall
Planning application reference
PA25/04503
Site area
25.3 ha
Address (REPD)
Trevarthian Farmhouse Plain An Gwarry Marazion
Council area (by location)
Cornwall
Time to decision
50 weeks
Name in REPD
Trevarthian Farmhouse - Solar PV Farm & Battery Energy Storage
REPD reference
9091

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bunkers Hillsolar farm5refused5.3
Lanyon Farmsolar farm12.8appeal withdrawn8.9
The Coach House, Gwinear Lane - Speedwell Solar Farmsolar farm40approved, not built9.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.1371, -5.4496).