Energy Projects Near You

Chester Energy (East Woolley Farm) (5 MW solar farm)

Chester Energy (East Woolley Farm) is a 5 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 June 2012; the record was last updated on 22 November 2012.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
22 November 2012record last updated
Cornwallcouncil area

Planning timeline

DateStage
17 December 2010Application submitted
18 April 2011Planning permission granted
1 June 2012Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
22 November 2012
Operator or applicant
Chester Energy (Eastcott)
Planning authority
Cornwall
Planning application reference
PA10/08695
Site area
20.3 ha
Address (REPD)
Land East Of East Woolley Farm, Morwenstow, Bude, Cornwall
Council area (by location)
Cornwall
Time to decision
17 weeks
REPD reference
1024

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Trentworthy Solar Farmsolar farm5application withdrawn3.6
Harbourcross wind farmwind farm10refused3.8
East Langford Farmsolar farm5operational7.2
Wheelers Crosswind farm7.8refused9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.9235, -4.4863).