Solar, wind and battery projects near Bracknell (RG42)
16 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of RG42 (Bracknell Forest): 2 are waiting for a planning decision, 14 approved but not yet running. The largest live scheme is Barkham Farms Solar Farm (33 MW solar farm, approved on 21 January 2022, not yet built; REPD status may be out of date), 9.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of RG42
Projects of 1 MW and more (3)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Billingbear Solar Farmsolar farm | solar farm | 21.5 | approved, not builtupdated Oct 2024 | Oct 2022 | granted Jul 2024 | Oct 2024 | Windsor and Maidenhead | 5.0 |
| Car Park Legoland Windsor Resort, Winkfield Road PV solar photovoltaicrooftop solar | rooftop solar | 1.2 | approved, not builtupdated Jun 2024 | May 2024 | granted Jun 2024 | Jun 2024 | Windsor and Maidenhead | 8.0 |
| Barkham Farms Solar Farmsolar farm | solar farm | 33 | approved, not built may be out of dateupdated Feb 2021 | Mar 2021 | granted Jan 2022 | Feb 2021 | Wokingham | 9.1 |
Smaller schemes under 1 MW, mostly rooftop solar (13)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| John Nike Way, Binfieldsolar farm | solar farm | 0.8 | application submittedupdated Mar 2026 | Feb 2026 | — | Mar 2026 | Bracknell Forest | 2.7 |
| David Lloyd Royal Berkshirerooftop solar | rooftop solar | — | approved, not builtupdated Sep 2025 | Jul 2025 | granted Sep 2025 | Sep 2025 | Bracknell Forest | 4.6 |
| Heatherwood Hospital, Brook Avenuerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jan 2026 | Oct 2025 | granted Dec 2025 | Jan 2026 | Windsor and Maidenhead | 5.2 |
| Heatherwood Hospital, Brook Avenuebattery storage | battery storage | — | approved, not builtupdated Jan 2026 | Dec 2025 | granted Jan 2026 | Jan 2026 | Windsor and Maidenhead | 5.2 |
| Ascot Racecourse, High Streetrooftop solar | rooftop solar | — | approved, not builtupdated Jun 2026 | Mar 2026 | granted Apr 2026 | Jun 2026 | Windsor and Maidenhead | 5.4 |
| Rectory Roadrooftop solar | rooftop solar | — | approved, not built may be out of dateupdated Apr 2021 | Jan 2021 | granted Apr 2021 | Apr 2021 | Wokingham | 5.7 |
| Broadmoor Hospital, Lower Broadmoor Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Apr 2026 | Mar 2025 | granted Feb 2026 | Apr 2026 | Bracknell Forest | 6.5 |
| The Paddock Centre, Joshua Jebb Wayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Feb 2025 | Dec 2024 | granted Jan 2025 | Feb 2025 | Bracknell Forest | 6.9 |
| Edgbarrow School, Grant Roadrooftop solar | rooftop solar | 0.2 | approved, not built | Apr 2026 | granted Jun 2026 | — | Bracknell Forest | 7.8 |
| Charters School, Charters Roadrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Jul 2024 | Apr 2024 | granted Jun 2024 | Jul 2024 | Windsor and Maidenhead | 8.3 |
| Windlesham Garden Centre, London Roadrooftop solar | rooftop solar | — | application submittedupdated Aug 2025 | Jul 2025 | — | Aug 2025 | Surrey Heath | 8.5 |
| Eskdale Road, Winnershrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2022 | Aug 2022 | granted Sep 2022 | Sep 2022 | Wokingham | 8.7 |
| Russells Farm, Windsor Great Parkrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Dec 2023 | Oct 2023 | granted Dec 2023 | Dec 2023 | Windsor and Maidenhead | 9.2 |
Distance from the average position of the RG42 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 3 | 1 | 2 | 0 | 0 | 55.3 |
| Rooftop solar | 12 | 1 | 11 | 0 | 0 | 3.2 |
| Battery storage | 1 | 0 | 1 | 0 | 0 | 0 |
MW in pipeline: pending, approved and under-construction capacity.
How Bracknell Forest decides solar, wind and battery applications
Bracknell Forest has 5 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.
All projects in Bracknell Forest
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near RG42, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.