Energy Projects Near You

Solar, wind and battery projects near London (SE21)

55 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SE21 (Southwark): 8 are waiting for a planning decision, 39 approved but not yet running, 1 operational. The largest live scheme is Solar Panels at Hedgehog Grove Solar Farm (98 MW solar farm, application submitted on 24 March 2026, no decision recorded), 8.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

55projects within 10 km
8awaiting a decision
39approved, not running
1operational

Projects within 10 km of SE21

Projects of 1 MW and more (7)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Selhurst Traincare Depot, Selhurst Roadrooftop solarrooftop solar1approved, not builtupdated Mar 2026Oct 2025granted Nov 2025Mar 2026Croydon5.3
Willow Lane Wind Turbineswind farmwind farm11abandonedupdated May 2014Jun 2004granted Aug 2004May 2014Merton7.0
Pegasus House, Sackville Streetrooftop solarrooftop solar2.3approved, not built may be out of dateupdated Dec 2021Nov 2021granted Dec 2021Dec 2021Westminster8.5
Solar Panels at Hedgehog Grove Solar Farmsolar farmsolar farm98application submittedupdated Apr 2026Mar 2026—Apr 2026Tower Hamlets8.6
Alcatel, Telegraph Houserooftop solarrooftop solar1.3refusedupdated Dec 2025Sep 2025refused Oct 2025Dec 2025Greenwich8.7
The O2 Arenawind farmwind farm3approved, not built may be out of dateupdated Oct 2021Jun 2021granted Sep 2021Oct 2021Greenwich9.5
Thameside DCrooftop solarrooftop solar1operationalupdated Feb 2016——Feb 2016Greenwich10.0
Smaller schemes under 1 MW, mostly rooftop solar (48)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Dulwich College, College Roadrooftop solarrooftop solar0.7approved, not builtupdated Feb 2025Jun 2024granted Dec 2024Feb 2025Southwark0.4
Knights Hill Solar PV equipmentrooftop solarrooftop solar0.2approved, not builtupdated Sep 2023Aug 2023granted Sep 2023Sep 2023Lambeth1.7
William Booth Training College, Champion Parkrooftop solarrooftop solar—approved, not built may be out of dateupdated Jul 2023Feb 2023granted Aug 2023Jul 2023Southwark3.2
William Booth Training College, Champion Parkrooftop solarrooftop solar—application submitted may be out of dateupdated Jul 2023Jul 2023—Jul 2023Southwark3.2
Streatham Ice & Leisure, Streatham High Road Solar Panels & ASHProoftop solarrooftop solar0.3approved, not builtupdated Mar 2024Nov 2023granted Mar 2024Mar 2024Lambeth3.4
Peckham Pulse Leisure Centre, Melon Roadrooftop solarrooftop solar0.2approved, not builtupdated Feb 2025Nov 2024granted Jan 2025Feb 2025Southwark4.1
45 Clapham Campus South Side - 525 Flats & Education Facilityrooftop solarrooftop solar0.2application submitted may be out of dateupdated Apr 2023Oct 2022—Apr 2023Lambeth4.3
The Spa, Beckenham Roadrooftop solarrooftop solar0.3approved, not builtupdated May 2023Feb 2023granted Apr 2023May 2023Bromley4.9
Sedgehill Academy, Sedgehill Roadrooftop solarrooftop solar0.4approved, not builtupdated Jan 2026Sep 2025granted Nov 2025Jan 2026Lewisham4.9
Battersea Studiosrooftop solarrooftop solar0.4approved, not builtupdated Sep 2024Jul 2024granted Sep 2024Sep 2024Wandsworth5.4
Walworth Academy, Shorncliffe Roadrooftop solarrooftop solar0.3approved, not builtupdated Feb 2024Dec 2023granted Jan 2024Feb 2024Southwark5.4
Croydon Roadrooftop solarrooftop solar0.2approved, not builtupdated Oct 2023Aug 2023granted Oct 2023Oct 2023Bromley5.5
Springfield University Hospital, Lapidge Driverooftop solarrooftop solar—refusedupdated Apr 2026Dec 2025refused Feb 2026Apr 2026Wandsworth5.7
Springfield University Hospitalrooftop solarrooftop solar—approved, not builtupdated Jun 2026Nov 2025granted May 2026Jun 2026Wandsworth5.8
City Of London Academyrooftop solarrooftop solar0.2approved, not built may be out of dateupdated May 2022Feb 2022granted May 2022May 2022Southwark5.8
David Lloyd Leisure, Stanhope Groverooftop solarrooftop solar0.5approved, not builtupdated Sep 2023Jul 2023granted Aug 2023Sep 2023Bromley6.1
Grosvenor Wing, St Georges Hospitalrooftop solarrooftop solar—approved, not builtupdated Mar 2026Dec 2025granted Feb 2026Mar 2026Wandsworth6.2
Dolphin Squarerooftop solarrooftop solar—under constructionupdated May 2022Apr 2022granted Dec 2022May 2022Westminster6.2
The Bermondsey Projectrooftop solarrooftop solar0.2approved, not builtupdated Oct 2023Oct 2017granted Jun 2020Oct 2023Southwark6.3
Trinity School Of John Whitgift, Shirley Roadrooftop solarrooftop solar—approved, not builtupdated Apr 2023Feb 2023granted Apr 2023Apr 2023Croydon6.6
Sainsburys Superstore, Merton High Streetrooftop solarrooftop solar1approved, not builtupdated Sep 2024Aug 2024granted Sep 2024Sep 2024Merton7.0
Downham Health & Leisure Centre, Moorside Roadrooftop solarrooftop solar0.2approved, not builtupdated Apr 2025Jan 2025granted Mar 2025Apr 2025Lewisham7.0
Consession Queen Mother Sports Centrerooftop solarrooftop solar—application submitted may be out of dateupdated Oct 2021Oct 2021—Oct 2021Westminster7.1
JJ Foodservice, South Wimbledonrooftop solarrooftop solar0.3application submittedupdated Nov 2024Sep 2024—Nov 2024Merton7.3
Sainsburys Supermarket, Trafalgar Wayrooftop solarrooftop solar0.6approved, not builtupdated Oct 2024Aug 2024granted Oct 2024Oct 2024Croydon7.3
Harbour club, Watermeadow Lanerooftop solarrooftop solar0.4application withdrawnupdated Jul 2024Nov 2023—Jul 2024Hammersmith and Fulham7.5
John Orwell Sports Centre, Tench Streetrooftop solarrooftop solar0.3approved, not builtupdated May 2025Feb 2025granted Apr 2025May 2025Tower Hamlets7.5
Bethlem Royal Hospital, Monks Orchard Road Solar Panels & Air Source Heat Pumpsrooftop solarrooftop solar—approved, not builtupdated Sep 2022May 2022granted Aug 2022Sep 2022Bromley7.6
Morden Road, South Wimbledonrooftop solarrooftop solar0.1approved, not builtupdated Sep 2024Aug 2024granted Aug 2024Sep 2024Merton7.8
Tower Place Westrooftop solarrooftop solar0.4approved, not builtupdated Mar 2025Jan 2025granted Feb 2025Mar 2025City of London7.8
Bethlem Royal Hospital, Monks Orchard Roadrooftop solarrooftop solar—application submittedMay 2026——Bromley8.0
J Sainsbury, Walters Yardrooftop solarrooftop solar0.2approved, not builtupdated Jun 2026Apr 2026granted Jun 2026Jun 2026Bromley8.0
The Highway - 114 Flats, Office Accomodation & Self Storage Facilityrooftop solarrooftop solar0.2approved, not builtupdated Jul 2024Dec 2021granted Aug 2023Jul 2024Tower Hamlets8.0
Cannon Streetrooftop solarrooftop solar0.3approved, not builtupdated Jan 2025Sep 2024granted Dec 2024Jan 2025City of London8.1
Paul Rhodes Bakery Limited, Lassell Streetrooftop solarrooftop solar—refusedupdated May 2025Mar 2025refused May 2025May 2025Greenwich8.1
Chelsea And Westminster Hospital, Fulham Road - Photovoltaic Panelsrooftop solarrooftop solar0.2approved, not builtupdated Jun 2026Mar 2026granted Apr 2026Jun 2026Kensington and Chelsea8.2
David Lloyd Leisure Limited, Corner Of Weigall Roadrooftop solarrooftop solar0.2approved, not builtupdated Sep 2023Jul 2023granted Sep 2023Sep 2023Greenwich8.3
Pavilion Leisure Centre, Kentish Wayrooftop solarrooftop solar0.2approved, not builtupdated Apr 2023Mar 2023granted Apr 2023Apr 2023Bromley8.4
Bush Houserooftop solarrooftop solar—approved, not built may be out of dateupdated Jun 2021Apr 2021granted May 2021Jun 2021Westminster8.4
Citibank, 25 Canada Square - Office Fit-Out & Refurbishmentrooftop solarrooftop solar—no application requiredupdated Feb 2022——Feb 2022Tower Hamlets8.7
Imperial College Health CentreSolar Panelsrooftop solarrooftop solar—application withdrawnupdated Apr 2021Feb 2021—Apr 2021Westminster8.8
Whitgift School, Nottingham Roadrooftop solarrooftop solar0.4application submitted may be out of dateupdated Sep 2022Aug 2022—Sep 2022Croydon8.8
Lindsey Streetrooftop solarrooftop solar0.2approved, not builtupdated Dec 2025Oct 2025granted Nov 2025Dec 2025City of London9.0
Millennium Retail Park - Flats & Retail Spacerooftop solarrooftop solar0.3application submitted may be out of dateupdated Sep 2024May 2024—Sep 2024Greenwich9.1
Westcroft Leisure Centre, Westcroft Roadrooftop solarrooftop solar0.3approved, not builtupdated Nov 2024Sep 2024granted Oct 2024Nov 2024Sutton9.3
David Lloyd Club, Bushey Roadrooftop solarrooftop solar0.8approved, not builtupdated Oct 2023Aug 2023granted Sep 2023Oct 2023Merton9.6
Fulham Pools, Lillie Roadrooftop solarrooftop solar0.3approved, not builtupdated May 2024Jan 2024granted Apr 2024May 2024Hammersmith and Fulham9.7
Jobcentreplus, Drysdale Streetrooftop solarrooftop solar—approved, not builtupdated Sep 2025May 2025granted Jul 2025Sep 2025Hackney9.9

Distance from the average position of the SE21 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm1100098
Rooftop solar527381313.9
Wind farm201003

MW in pipeline: pending, approved and under-construction capacity.

How Southwark decides solar, wind and battery applications

Southwark has 6 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

All projects in Southwark

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near SE21, 10 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.