Energy Projects Near You

Solar, wind and battery projects near Sevenoaks (TN14)

8 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TN14 (Sevenoaks): 4 approved but not yet running. The largest live scheme is Biggin Hill Airport, Main Road (12 MW rooftop solar, under construction since 1 October 2023), 9.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8projects within 10 km
0awaiting a decision
4approved, not running
0operational

Projects within 10 km of TN14

Projects of 1 MW and more (2)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Biggin Hill Airport, Main Roadrooftop solarrooftop solar12under constructionupdated Dec 2023——Dec 2023Bromley9.7
West Kingdownsolar farmsolar farm20application withdrawnupdated Jan 2014Aug 2013—Jan 2014Sevenoaks9.9
Smaller schemes under 1 MW, mostly rooftop solar (6)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
The Sennocke Centre, High Street Solar PV Systemsrooftop solarrooftop solar0.4approved, not builtupdated May 2024Mar 2024granted May 2024May 2024Sevenoaks4.7
Turners Gardens, Weald Roadbattery storagebattery storage0.2refusedupdated Mar 2026Dec 2025refused Feb 2026Mar 2026Sevenoaks5.1
St Julians, St Julians Roadrooftop solarrooftop solar0.3application withdrawnupdated Oct 2023May 2023—Oct 2023Sevenoaks6.7
Commonwork Organic Farms Limited, Bore Placerooftop solarrooftop solar0.2approved, not builtupdated Nov 2023Sep 2023granted Nov 2023Nov 2023Sevenoaks8.6
Commonwork Organic Farms Limited, Bore Placebattery storagebattery storage—approved, not builtupdated Nov 2023Sep 2023granted Nov 2023Nov 2023Sevenoaks8.6
Nizels Golf Club, Nizels Lanerooftop solarrooftop solar0.1refusedupdated Mar 2024Jan 2024refused Feb 2024Mar 2024Tonbridge and Malling9.5

Distance from the average position of the TN14 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm100000
Rooftop solar5030112.5
Battery storage201010

MW in pipeline: pending, approved and under-construction capacity.

How Sevenoaks decides solar, wind and battery applications

ApplicationsSevenoaksUK
Decided applications (solar, wind, battery)1110,236
Refused4 (36%)19%
Solar refused2 of 712%
Battery storage refused2 of 416%
Median time from submission to decision10.3 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

All projects in Sevenoaks

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.