Energy Projects Near You

Solar, wind and battery projects near Sevenoaks (TN13)

9 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TN13 (Sevenoaks): 3 are waiting for a planning decision, 3 approved but not yet running. The largest live scheme is Stangate West Landfill Site, Quarry Hill Road Solar Park & Battery (6 MW solar farm, application submitted on 11 May 2026, no decision recorded), 8.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9projects within 10 km
3awaiting a decision
3approved, not running
0operational

Projects within 10 km of TN13

Projects of 1 MW and more (1)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Stangate West Landfill Site, Quarry Hill Road Solar Park & Batterysolar farmsolar farm6application submittedMay 2026——Tonbridge and Malling8.4
Smaller schemes under 1 MW, mostly rooftop solar (8)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
The Sennocke Centre, High Street Solar PV Systemsrooftop solarrooftop solar0.4approved, not builtupdated May 2024Mar 2024granted May 2024May 2024Sevenoaks1.7
Turners Gardens, Weald Roadbattery storagebattery storage0.2refusedupdated Mar 2026Dec 2025refused Feb 2026Mar 2026Sevenoaks2.1
St Julians, St Julians Roadrooftop solarrooftop solar0.3application withdrawnupdated Oct 2023May 2023—Oct 2023Sevenoaks3.7
Commonwork Organic Farms Limited, Bore Placerooftop solarrooftop solar0.2approved, not builtupdated Nov 2023Sep 2023granted Nov 2023Nov 2023Sevenoaks6.6
Commonwork Organic Farms Limited, Bore Placebattery storagebattery storage—approved, not builtupdated Nov 2023Sep 2023granted Nov 2023Nov 2023Sevenoaks6.6
Nizels Golf Club, Nizels Lanerooftop solarrooftop solar0.1refusedupdated Mar 2024Jan 2024refused Feb 2024Mar 2024Tonbridge and Malling6.6
Stangate West Landfill Site, Quarry Hill Road Solar Park & Batterybattery storagebattery storage—application submittedMay 2026——Tonbridge and Malling8.4
Platt Industrial Estate,Maidstone Road - Micro Energy Storage Facilitybattery storagebattery storage0.2application submittedupdated Nov 2024Oct 2024—Nov 2024Tonbridge and Malling8.8

Distance from the average position of the TN13 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm110006
Rooftop solar402010.5
Battery storage421010.2

MW in pipeline: pending, approved and under-construction capacity.

How Sevenoaks decides solar, wind and battery applications

ApplicationsSevenoaksUK
Decided applications (solar, wind, battery)1110,236
Refused4 (36%)19%
Solar refused2 of 712%
Battery storage refused2 of 416%
Median time from submission to decision10.3 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

All projects in Sevenoaks

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.