Solar, wind and battery projects near Tonbridge (TN10)

27 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TN10 (Tonbridge and Malling): 7 are waiting for a planning decision, 13 approved but not yet running, 3 operational. The largest live scheme is Solar Farm & Battery Storage at Reeds Solar Farm Alders Road Colts Hill (20 MW battery storage, approved on 6 March 2025, not yet built), 6.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

27projects within 10 km
7awaiting a decision
13approved, not running
3operational

Projects within 10 km of TN10

Projects of 1 MW and more (9)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Hadlow Place solar farmsolar farmsolar farm14.3operationalupdated May 2015Mar 2014granted Nov 2014May 2015Tunbridge Wells4.8
Capel Grange Solar Parksolar farmsolar farm6.6operationalupdated Jun 2016Dec 2014granted Apr 2015Jun 2016Tunbridge Wells6.5
Capel Grangesolar farmsolar farm10.4refusedupdated Sep 2014Feb 2014refused Sep 2014Sep 2014Tunbridge Wells6.5
Solar Farm & Battery Storage at Reeds Solar Farm Alders Road Colts Hillbattery storagebattery storage20approved, not builtupdated Feb 2026Dec 2022granted Mar 2025Feb 2026Tunbridge Wells6.6
Solar Farm & Battery Storage at Reeds Solar Farm Alders Road Colts Hillsolar farmsolar farm10approved, not builtupdated Feb 2026Dec 2022granted Mar 2025Feb 2026Tunbridge Wells6.6
Stangate West Landfill Site, Quarry Hill Road Solar Park & Batterysolar farmsolar farm6application submittedMay 2026——Tonbridge and Malling8.6
Manor Farm, Laddingfordsolar farmsolar farm4.9application submittedupdated May 2026Apr 2026—May 2026Maidstone9.6
Manor Farm, Laddingford Solar Farmsolar farmsolar farm4.9application submittedupdated May 2026Mar 2026—May 2026Maidstone9.6
Paddock Woodsolar farmsolar farm9.2operationalupdated Jul 2015Sep 2014granted Dec 2014Jul 2015Tunbridge Wells9.9
Smaller schemes under 1 MW, mostly rooftop solar (18)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
The Tonbridge School Centre, London Roadrooftop solarrooftop solar0.3approved, not builtupdated Feb 2024Dec 2023granted Feb 2024Feb 2024Tonbridge and Malling1.3
Nizels Golf Club, Nizels Lanerooftop solarrooftop solar0.1refusedupdated Mar 2024Jan 2024refused Feb 2024Mar 2024Tonbridge and Malling4.7
Moat Farm, Five Oak Greenrooftop solarrooftop solar0.2approved, not builtupdated Oct 2021Aug 2021granted Oct 2021Oct 2021Tunbridge Wells5.5
Moat Farm, Whetsted Roadrooftop solarrooftop solar0.3approved, not builtupdated Sep 2023Jul 2023granted Sep 2023Sep 2023Tunbridge Wells5.5
Adrian Scripps, Moat Farmrooftop solarrooftop solar0.3approved, not builtupdated Dec 2025Sep 2025granted Nov 2025Dec 2025Tunbridge Wells5.6
Longfield Road, Royal Tunbridge Wellsrooftop solarrooftop solar0.1approved, not builtupdated May 2022Apr 2022granted May 2022May 2022Tunbridge Wells6.2
Fountains Retail Park, Dowding Wayrooftop solarrooftop solar—approved, not builtupdated Nov 2025Sep 2025granted Oct 2025Nov 2025Tunbridge Wells6.2
Micro energy storage facilitybattery storagebattery storage0.2approved, not builtupdated Jul 2024Apr 2024granted Jun 2024Jul 2024Tunbridge Wells6.3
St Julians, St Julians Roadrooftop solarrooftop solar0.3application withdrawnupdated Oct 2023May 2023—Oct 2023Sevenoaks6.4
Turners Gardens, Weald Roadbattery storagebattery storage0.2refusedupdated Mar 2026Dec 2025refused Feb 2026Mar 2026Sevenoaks8.1
The Sennocke Centre, High Street Solar PV Systemsrooftop solarrooftop solar0.4approved, not builtupdated May 2024Mar 2024granted May 2024May 2024Sevenoaks8.4
Transfesa Road, Paddock Woodrooftop solarrooftop solar0.9application submitted may be out of dateupdated Jul 2022May 2022—Jul 2022Tunbridge Wells8.5
Stangate West Landfill Site, Quarry Hill Road Solar Park & Batterybattery storagebattery storage—application submittedMay 2026——Tonbridge and Malling8.6
Car park, Royal Victoria Place Solar Car port Canopiesrooftop solarrooftop solar—application submittedupdated Oct 2025Sep 2025—Oct 2025Tunbridge Wells8.7
Platt Industrial Estate,Maidstone Road - Micro Energy Storage Facilitybattery storagebattery storage0.2application submittedupdated Nov 2024Oct 2024—Nov 2024Tonbridge and Malling9.0
Commonwork Organic Farms Limited, Bore Placerooftop solarrooftop solar0.2approved, not builtupdated Nov 2023Sep 2023granted Nov 2023Nov 2023Sevenoaks9.0
Commonwork Organic Farms Limited, Bore Placebattery storagebattery storage—approved, not builtupdated Nov 2023Sep 2023granted Nov 2023Nov 2023Sevenoaks9.0
Sainsburys, Linden Park Roadrooftop solarrooftop solar0.4approved, not builtupdated May 2025Mar 2025granted Apr 2025May 2025Tunbridge Wells10.0

Distance from the average position of the TN10 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm8313125.8
Rooftop solar1329013.1
Battery storage6230120.4

MW in pipeline: pending, approved and under-construction capacity.

How Tonbridge and Malling decides solar, wind and battery applications

ApplicationsTonbridge and MallingUK
Decided applications (solar, wind, battery)1210,236
Refused1 (8%)19%
Solar refused1 of 812%
Battery storage refused0 of 416%
Median time from submission to decision10.4 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Tonbridge and Malling

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near TN10, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.