Solar, wind and battery projects near Maidstone (ME18)
38 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of ME18 (Maidstone): 10 are waiting for a planning decision, 18 approved but not yet running, 8 operational. The largest live scheme is Eckley Farms, Marden Solar Energy Farm (49.9 MW solar farm, approved on 5 February 2024, not yet built), 8.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of ME18
Projects of 1 MW and more (16)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Manor Farm, Laddingfordsolar farm | solar farm | 4.9 | application submittedupdated May 2026 | Apr 2026 | — | May 2026 | Maidstone | 3.5 |
| Manor Farm, Laddingford Solar Farmsolar farm | solar farm | 4.9 | application submittedupdated May 2026 | Mar 2026 | — | May 2026 | Maidstone | 3.5 |
| Kingshill Solar Farmsolar farm | solar farm | 3 | operationalupdated Aug 2024 | Sep 2021 | granted Dec 2021 | Aug 2024 | Tonbridge and Malling | 4.8 |
| Offham Landfill Sitesolar farm | solar farm | 10.2 | under constructionupdated Apr 2024 | Apr 2021 | granted Oct 2023 | Apr 2024 | Tonbridge and Malling | 6.4 |
| Paddock Woodsolar farm | solar farm | 9.2 | operationalupdated Jul 2015 | Sep 2014 | granted Dec 2014 | Jul 2015 | Tunbridge Wells | 7.7 |
| Hadlow Place solar farmsolar farm | solar farm | 14.3 | operationalupdated May 2015 | Mar 2014 | granted Nov 2014 | May 2015 | Tunbridge Wells | 8.0 |
| Capel Grangesolar farm | solar farm | 10.4 | refusedupdated Sep 2014 | Feb 2014 | refused Sep 2014 | Sep 2014 | Tunbridge Wells | 8.1 |
| Capel Grange Solar Parksolar farm | solar farm | 6.6 | operationalupdated Jun 2016 | Dec 2014 | granted Apr 2015 | Jun 2016 | Tunbridge Wells | 8.1 |
| Eckley Farms, Marden Solar Energy Farmsolar farm | solar farm | 49.9 | approved, not builtupdated Feb 2024 | Jun 2022 | granted Feb 2024 | Feb 2024 | Maidstone | 8.3 |
| Pattenden Lane Solar PV Energysolar farm | solar farm | 19 | application submittedupdated Feb 2025 | Dec 2024 | — | Feb 2025 | Maidstone | 8.3 |
| Land off Ford Lanesolar farm | solar farm | 4.7 | operationalupdated Feb 2017 | Jul 2015 | granted Nov 2015 | Feb 2017 | Tonbridge and Malling | 8.7 |
| Aylesford BESSbattery storage | battery storage | 29 | operationalupdated Mar 2026 | Sep 2017 | granted Dec 2017 | Mar 2026 | Tonbridge and Malling | 8.7 |
| Solar Farm & Battery Storage at Reeds Solar Farm Alders Road Colts Hillbattery storage | battery storage | 20 | approved, not builtupdated Feb 2026 | Dec 2022 | granted Mar 2025 | Feb 2026 | Tunbridge Wells | 9.1 |
| Solar Farm & Battery Storage at Reeds Solar Farm Alders Road Colts Hillsolar farm | solar farm | 10 | approved, not builtupdated Feb 2026 | Dec 2022 | granted Mar 2025 | Feb 2026 | Tunbridge Wells | 9.1 |
| Stangate West Landfill Site, Quarry Hill Road Solar Park & Batterysolar farm | solar farm | 6 | application submitted | May 2026 | — | — | Tonbridge and Malling | 9.4 |
| Biossence Solar Parksolar farm | solar farm | 4.5 | operationalupdated Mar 2013 | Apr 2011 | granted Jun 2011 | Mar 2013 | Tonbridge and Malling | 9.9 |
Smaller schemes under 1 MW, mostly rooftop solar (22)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Coxheath County Primary School, Stockett Lanerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2026 | Oct 2025 | granted Dec 2025 | Jan 2026 | Maidstone | 5.6 |
| Nutriblend House, Mills Roadrooftop solar | rooftop solar | 0.3 | application submitted | May 2026 | — | — | Tonbridge and Malling | 6.3 |
| Mid Kent College, Tonbridge Roadrooftop solar | rooftop solar | 0.3 | application submitted may be out of dateupdated Jul 2023 | Jul 2023 | — | Jul 2023 | Maidstone | 6.4 |
| Mid Kent College, Tonbridge Road - Air Source Heat Pumps & Solar Panelssolar farm | solar farm | 0.3 | approved, not builtupdated Apr 2024 | Feb 2024 | granted Apr 2024 | Apr 2024 | Maidstone | 6.4 |
| Berry Gardens, Redwall Lanerooftop solar | rooftop solar | 0.6 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Aug 2023 | Sep 2023 | Maidstone | 6.5 |
| Transfesa Road, Paddock Woodrooftop solar | rooftop solar | 0.9 | application submitted may be out of dateupdated Jul 2022 | May 2022 | — | Jul 2022 | Tunbridge Wells | 6.5 |
| Moat Farm, Whetsted Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Sep 2023 | Sep 2023 | Tunbridge Wells | 7.2 |
| Adrian Scripps, Moat Farmrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Dec 2025 | Sep 2025 | granted Nov 2025 | Dec 2025 | Tunbridge Wells | 7.3 |
| Moat Farm, Five Oak Greenrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Oct 2021 | Aug 2021 | granted Oct 2021 | Oct 2021 | Tunbridge Wells | 7.4 |
| Larkfield Leisure Centre, New Hythe Lanerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2025 | Oct 2024 | granted Dec 2024 | Jan 2025 | Tonbridge and Malling | 7.6 |
| Lockmeadow Centre, Barker Roadrooftop solar | rooftop solar | 0.4 | application withdrawnupdated Nov 2025 | Jun 2025 | — | Nov 2025 | Maidstone | 7.8 |
| St Leonards Roadrooftop solar | rooftop solar | 0.1 | approved, not builtupdated May 2022 | Apr 2022 | granted Jun 2022 | May 2022 | Maidstone | 8.0 |
| Eckley Farms, Marden Solar Energy Farmbattery storage | battery storage | — | approved, not builtupdated Feb 2024 | Jun 2022 | granted Feb 2024 | Feb 2024 | Maidstone | 8.3 |
| Unit A Riverside Business Parkrooftop solar | rooftop solar | 1 | approved, not builtupdated May 2022 | May 2022 | granted Jul 2022 | May 2022 | Tonbridge and Malling | 8.7 |
| Corona Terrace & Hollow Lane - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated Jun 2026 | Nov 2025 | granted May 2026 | Jun 2026 | Tonbridge and Malling | 8.7 |
| Churn Lane, Horsmonden Solar Panelssolar farm | solar farm | 0.5 | operationalupdated Nov 2021 | Feb 2021 | granted Jun 2021 | Nov 2021 | Tunbridge Wells | 8.8 |
| Corona Terrace And Hollow Lane - Micro Energy Storage Systembattery storage | battery storage | 0.2 | application submittedupdated Dec 2025 | Nov 2025 | — | Dec 2025 | Tonbridge and Malling | 8.8 |
| W M Morrisons Supermarketsrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Mar 2022 | Feb 2022 | granted Apr 2022 | Mar 2022 | Maidstone | 9.2 |
| Platt Industrial Estate,Maidstone Road - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | application submittedupdated Nov 2024 | Oct 2024 | — | Nov 2024 | Tonbridge and Malling | 9.3 |
| Stangate West Landfill Site, Quarry Hill Road Solar Park & Batterybattery storage | battery storage | — | application submitted | May 2026 | — | — | Tonbridge and Malling | 9.4 |
| Mackenders Close - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated Mar 2025 | Oct 2024 | granted Jan 2025 | Mar 2025 | Tonbridge and Malling | 9.5 |
| East Hill Farmsolar farm | solar farm | — | approved, not builtupdated Sep 2023 | Jul 2023 | granted Sep 2023 | Sep 2023 | Maidstone | 9.8 |
Distance from the average position of the ME18 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 17 | 4 | 5 | 7 | 1 | 105 |
| Rooftop solar | 13 | 3 | 9 | 0 | 0 | 4.8 |
| Battery storage | 8 | 3 | 4 | 1 | 0 | 20.8 |
MW in pipeline: pending, approved and under-construction capacity.
How Maidstone decides solar, wind and battery applications
| Applications | Maidstone | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 21 | 10,236 |
| Refused | 6 (29%) | 19% |
| Solar refused | 5 of 20 | 12% |
| Battery storage refused | 1 of 1 | 16% |
| Median time from submission to decision | 8.1 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 2 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near ME18, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.