Eckley Farms, Marden Solar Energy Farm (49.9 MW)

Eckley Farms, Marden Solar Energy Farm is a 49.9 MW solar farm project in Maidstone, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 5 February 2024, not yet built; the record was last updated on 13 February 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
13 February 2024record last updated
Maidstonecouncil area

Planning timeline

DateStage
1 June 2022Application submitted
28 October 2022Refused by the planning authority
5 February 2024Planning permission granted
5 February 2024Appeal allowed

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
13 February 2024
Operator or applicant
Statkraft Wind UK Limited
Planning authority
Maidstone
Planning application reference
22/501335/FULL
Site area
74.5 ha
Address (REPD)
N/O Little Cheveney Farm, Sheephurst Lane, Marden
Council area (by location)
Maidstone
Time to decision
88 weeks
Contracts for Difference
AR6
Name in REPD
Eckley Farms, Marden - Solar Energy Farm
REPD reference
9194

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsMaidstoneUK
Decided applications (solar, wind, battery)2110,236
Refused6 (29%)19%
Solar refused5 of 2012%
Battery storage refused1 of 116%
Median time from submission to decision8.1 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Pattenden Lane Solar PV Energysolar farm19application submitted1.7
Widehurst Farmsolar farm5operational3.4
Maidstone Road, Horsmonden - Paddock Solar Farmsolar farm49.9under construction3.6
Great Pagehurst Farmsolar farm13.6refused on appeal3.7
Paddock Woodsolar farm9.2operational3.8
Solar PV Farmsolar farm18application submitted6.1
Capel Grangesolar farm10.4refused7.4
Capel Grange Solar Parksolar farm6.6operational7.4
Solar Farm & Battery Storage at Reeds Solar Farm Alders Road Colts Hillsolar farm10approved, not built8.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1745, 0.4662).