Widehurst Farm (5 MW solar farm)

Widehurst Farm is a 5 MW solar farm project in Maidstone, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 March 2017; the record was last updated on 18 July 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
18 July 2017record last updated
Maidstonecouncil area

Planning timeline

DateStage
1 October 2015Application submitted
3 March 2016Planning permission granted
7 November 2016Construction started
15 March 2017Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
18 July 2017
Operator or applicant
Wirsol (formerly Susenco)
Planning authority
Maidstone
Planning application reference
15/505971/FULL
Site area
11.5 ha
Address (REPD)
Land At Widehurst Farm, Thorn Road, Marden, Tonbridge
Council area (by location)
Maidstone
Time to decision
22 weeks
REPD reference
5824

Who decides

ApplicationsMaidstoneUK
Decided applications (solar, wind, battery)2110,236
Refused6 (29%)19%
Solar refused5 of 2012%
Battery storage refused1 of 116%
Median time from submission to decision8.1 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Great Pagehurst Farmsolar farm13.6refused on appeal1.6
Solar PV Farmsolar farm18application submitted2.8
Pattenden Lane Solar PV Energysolar farm19application submitted2.9
Eckley Farms, Marden Solar Energy Farmsolar farm49.9approved, not built3.4
Maidstone Road, Horsmonden - Paddock Solar Farmsolar farm49.9under construction5.3
Land At Pullen Farmsolar farm10refused on appeal5.7
Paddock Woodsolar farm9.2operational6.9
Huggin's Hall (Extension)battery storage9.9permission expired7.3
Huggin's Hallbattery storage40operational7.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1593, 0.5089).