Energy Projects Near You

Great Pagehurst Farm (13.6 MW solar farm)

Great Pagehurst Farm is a 13.6 MW solar farm project in Maidstone, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 10 April 2017; the record was last updated on 26 April 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13.6 MWsolar farm
refused on appealstatus in REPD
26 April 2017record last updated
Maidstonecouncil area

Planning timeline

DateStage
19 September 2013Application submitted
11 February 2016Refused by the planning authority
22 April 2016Appeal lodged
10 April 2017Appeal refused

Project details

Technology
solar farm
Capacity
13.6 MW
Status (REPD)
refused on appeal
Record last updated
26 April 2017
Operator or applicant
Sunsave 22 (Pagehurst Farm) Limited
Planning authority
Maidstone
Planning application reference
13/1456
Appeal reference
APP/U2235/W/16/3146969
Site area
20.5 ha
Address (REPD)
Great Pagehurst Farm, Pagehurst Road, Staplehurst, Tonbridge, Kent
Council area (by location)
Maidstone
Time to decision
125 weeks
REPD reference
2315

Who decides

ApplicationsMaidstoneUK
Decided applications (solar, wind, battery)2110,236
Refused6 (29%)19%
Solar refused5 of 2012%
Battery storage refused1 of 116%
Median time from submission to decision8.1 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Widehurst Farmsolar farm5operational1.6
Pattenden Lane Solar PV Energysolar farm19application submitted2.4
Eckley Farms, Marden Solar Energy Farmsolar farm49.9approved, not built3.7
Solar PV Farmsolar farm18application submitted3.9
Land At Pullen Farmsolar farm10refused on appeal5.5
Maidstone Road, Horsmonden - Paddock Solar Farmsolar farm49.9under construction6.4
Paddock Woodsolar farm9.2operational7.4
Huggin's Hall (Extension)battery storage9.9permission expired8.8
Huggin's Hallbattery storage40operational8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1727, 0.5185).