Solar, wind and battery projects near Maidstone (ME15)
27 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of ME15 (Maidstone): 5 are waiting for a planning decision, 15 approved but not yet running, 2 operational. The largest live scheme is Eckley Farms, Marden Solar Energy Farm (49.9 MW solar farm, approved on 5 February 2024, not yet built), 9.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of ME15
Projects of 1 MW and more (9)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Harp Farm Solar Parksolar farm | solar farm | 15 | refusedupdated Jun 2026 | Jun 2025 | refused Apr 2026 | Jun 2026 | Maidstone | 6.4 |
| Biossence Solar Parksolar farm | solar farm | 4.5 | operationalupdated Mar 2013 | Apr 2011 | granted Jun 2011 | Mar 2013 | Tonbridge and Malling | 8.3 |
| Pattenden Lane Solar PV Energysolar farm | solar farm | 19 | application submittedupdated Feb 2025 | Dec 2024 | — | Feb 2025 | Maidstone | 8.6 |
| Aylesford BESSbattery storage | battery storage | 29 | operationalupdated Mar 2026 | Sep 2017 | granted Dec 2017 | Mar 2026 | Tonbridge and Malling | 8.8 |
| Great Pagehurst Farmsolar farm | solar farm | 13.6 | refused on appealupdated Apr 2017 | Sep 2013 | refused Feb 2016 | Apr 2017 | Maidstone | 9.0 |
| Manor Farm, Laddingfordsolar farm | solar farm | 4.9 | application submittedupdated May 2026 | Apr 2026 | — | May 2026 | Maidstone | 9.1 |
| Manor Farm, Laddingford Solar Farmsolar farm | solar farm | 4.9 | application submittedupdated May 2026 | Mar 2026 | — | May 2026 | Maidstone | 9.1 |
| Great Tong Solar Farmsolar farm | solar farm | 4.9 | appeal withdrawnupdated Aug 2018 | Aug 2015 | refused Feb 2016 | Aug 2018 | Maidstone | 9.4 |
| Eckley Farms, Marden Solar Energy Farmsolar farm | solar farm | 49.9 | approved, not builtupdated Feb 2024 | Jun 2022 | granted Feb 2024 | Feb 2024 | Maidstone | 9.9 |
Smaller schemes under 1 MW, mostly rooftop solar (18)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| W M Morrisons Supermarketsrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Mar 2022 | Feb 2022 | granted Apr 2022 | Mar 2022 | Maidstone | 1.2 |
| Lockmeadow Centre, Barker Roadrooftop solar | rooftop solar | 0.4 | application withdrawnupdated Nov 2025 | Jun 2025 | — | Nov 2025 | Maidstone | 2.2 |
| Maidstone Borough Council Depot, Bircholt Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2025 | Feb 2025 | granted May 2025 | May 2025 | Maidstone | 2.6 |
| Mid Kent College, Tonbridge Road - Air Source Heat Pumps & Solar Panelssolar farm | solar farm | 0.3 | approved, not builtupdated Apr 2024 | Feb 2024 | granted Apr 2024 | Apr 2024 | Maidstone | 3.3 |
| Mid Kent College, Tonbridge Roadrooftop solar | rooftop solar | 0.3 | application submitted may be out of dateupdated Jul 2023 | Jul 2023 | — | Jul 2023 | Maidstone | 3.3 |
| Coxheath County Primary School, Stockett Lanerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2026 | Oct 2025 | granted Dec 2025 | Jan 2026 | Maidstone | 3.5 |
| Sutton Road, Langleyrooftop solar | rooftop solar | 0.8 | approved, not builtupdated Apr 2025 | Feb 2025 | granted Apr 2025 | Apr 2025 | Maidstone | 3.6 |
| East Hill Farmsolar farm | solar farm | — | approved, not builtupdated Sep 2023 | Jul 2023 | granted Sep 2023 | Sep 2023 | Maidstone | 4.0 |
| Ledian Farm, Upper Streetrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2024 | Jan 2024 | granted Feb 2024 | Mar 2024 | Maidstone | 5.1 |
| St Leonards Roadrooftop solar | rooftop solar | 0.1 | approved, not builtupdated May 2022 | Apr 2022 | granted Jun 2022 | May 2022 | Maidstone | 5.1 |
| Berry Gardens, Redwall Lanerooftop solar | rooftop solar | 0.6 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Aug 2023 | Sep 2023 | Maidstone | 5.2 |
| Nutriblend House, Mills Roadrooftop solar | rooftop solar | 0.3 | application submitted | May 2026 | — | — | Tonbridge and Malling | 6.3 |
| Event Centre, Detling Hillrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jun 2026 | Mar 2026 | granted May 2026 | Jun 2026 | Maidstone | 6.4 |
| Mackenders Close - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated Mar 2025 | Oct 2024 | granted Jan 2025 | Mar 2025 | Tonbridge and Malling | 8.0 |
| Larkfield Leisure Centre, New Hythe Lanerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2025 | Oct 2024 | granted Dec 2024 | Jan 2025 | Tonbridge and Malling | 8.8 |
| Unit A Riverside Business Parkrooftop solar | rooftop solar | 1 | approved, not builtupdated May 2022 | May 2022 | granted Jul 2022 | May 2022 | Tonbridge and Malling | 8.8 |
| Sainsburys Supermarkets, Station Roadrooftop solar | rooftop solar | 0.2 | refusedupdated Jul 2023 | May 2023 | refused Jun 2023 | Jul 2023 | Maidstone | 9.4 |
| Eckley Farms, Marden Solar Energy Farmbattery storage | battery storage | — | approved, not builtupdated Feb 2024 | Jun 2022 | granted Feb 2024 | Feb 2024 | Maidstone | 9.9 |
Distance from the average position of the ME15 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 10 | 3 | 3 | 1 | 2 | 79 |
| Rooftop solar | 14 | 2 | 10 | 0 | 1 | 4.5 |
| Battery storage | 3 | 0 | 2 | 1 | 0 | 0.2 |
MW in pipeline: pending, approved and under-construction capacity.
How Maidstone decides solar, wind and battery applications
| Applications | Maidstone | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 21 | 10,236 |
| Refused | 6 (29%) | 19% |
| Solar refused | 5 of 20 | 12% |
| Battery storage refused | 1 of 1 | 16% |
| Median time from submission to decision | 8.1 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 2 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near ME15, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.