Energy Projects Near You

Maidstone Road, Horsmonden - Paddock Solar Farm (49.9 MW)

Maidstone Road, Horsmonden - Paddock Solar Farm is a 49.9 MW solar farm project in Tunbridge Wells, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 10 April 2024; the record was last updated on 12 April 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
under constructionstatus in REPD
12 April 2024record last updated
Tunbridge Wellscouncil area

Planning timeline

DateStage
20 September 2022Application submitted
19 December 2022Refused by the planning authority
5 September 2023Planning permission granted
10 April 2024Construction started

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
under construction
Record last updated
12 April 2024
Operator or applicant
Voltalia UK
Planning authority
Tunbridge Wells
Planning application reference
22/02773/FULL
Site area
69.2 ha
Address (REPD)
Bockingfold Farm Maidstone Road Horsmonden
Council area (by location)
Tunbridge Wells
Time to decision
50 weeks
Contracts for Difference
AR5
REPD reference
10577

Who decides

ApplicationsTunbridge WellsUK
Decided applications (solar, wind, battery)2510,236
Refused7 (28%)19%
Solar refused5 of 2012%
Battery storage refused2 of 516%
Median time from submission to decision15.0 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Paddock Woodsolar farm9.2operational3.1
Eckley Farms, Marden Solar Energy Farmsolar farm49.9approved, not built3.6
Pattenden Lane Solar PV Energysolar farm19application submitted5.2
Widehurst Farmsolar farm5operational5.3
Capel Grangesolar farm10.4refused6.2
Capel Grange Solar Parksolar farm6.6operational6.2
Solar Farm & Battery Storage at Reeds Solar Farm Alders Road Colts Hillsolar farm10approved, not built6.3
Great Pagehurst Farmsolar farm13.6refused on appeal6.4
Solar PV Farmsolar farm18application submitted6.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1486, 0.4345).