Energy Projects Near You

Solar Farm & Battery Storage at Reeds Solar Farm Alders Road Colts Hill (10 MW)

Solar Farm & Battery Storage at Reeds Solar Farm Alders Road Colts Hill is a 10 MW solar farm project in Tunbridge Wells, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 6 March 2025, not yet built; the record was last updated on 20 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWsolar farm
approved, not builtstatus in REPD
20 February 2026record last updated
Tunbridge Wellscouncil area

Planning timeline

DateStage
15 December 2022Application submitted
6 March 2025Planning permission granted
6 March 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
10 MW
Status (REPD)
approved, not built
Record last updated
20 February 2026
Operator or applicant
Low Carbon
Planning authority
Tunbridge Wells
Planning application reference
22/03563/FULL
Site area
9.8 ha
Address (REPD)
Reeds Solar Farm Alders Road Colts Hill
Council area (by location)
Tunbridge Wells
Time to decision
116 weeks
Contracts for Difference
AR7a
Name in REPD
Reeds Solar Farm, Alders Road - Solar Farm & Battery Storage
REPD reference
12940

The scheme also includes 20 MW of battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsTunbridge WellsUK
Decided applications (solar, wind, battery)2510,236
Refused7 (28%)19%
Solar refused5 of 2012%
Battery storage refused2 of 516%
Median time from submission to decision15.0 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Capel Grange Solar Parksolar farm6.6operational1.0
Capel Grangesolar farm10.4refused1.0
Hadlow Place solar farmsolar farm14.3operational2.0
Paddock Woodsolar farm9.2operational4.2
Maidstone Road, Horsmonden - Paddock Solar Farmsolar farm49.9under construction6.3
Eckley Farms, Marden Solar Energy Farmsolar farm49.9approved, not built8.0
Pattenden Lane Solar PV Energysolar farm19application submitted9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1705, 0.3516).