Capel Grange Solar Park (6.6 MW)

Capel Grange Solar Park is a 6.6 MW solar farm project in Tunbridge Wells, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2016; the record was last updated on 20 June 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.6 MWsolar farm
operationalstatus in REPD
20 June 2016record last updated
Tunbridge Wellscouncil area

Planning timeline

DateStage
12 December 2014Application submitted
10 April 2015Planning permission granted
1 November 2015Construction started
31 March 2016Operational

Project details

Technology
solar farm
Capacity
6.6 MW
Status (REPD)
operational
Record last updated
20 June 2016
Operator or applicant
West Coast Energy
Planning authority
Tunbridge Wells
Planning application reference
14/506168/FULL
Site area
22.3 ha
Address (REPD)
OS Plot 8200, Badsell Road, Five Oak Green, Tonbridge
Council area (by location)
Tunbridge Wells
Time to decision
17 weeks
REPD reference
4936

Who decides

ApplicationsTunbridge WellsUK
Decided applications (solar, wind, battery)2510,236
Refused7 (28%)19%
Solar refused5 of 2012%
Battery storage refused2 of 516%
Median time from submission to decision15.0 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Capel Grangesolar farm10.4refused<0.1
Solar Farm & Battery Storage at Reeds Solar Farm Alders Road Colts Hillsolar farm10approved, not built1.0
Hadlow Place solar farmsolar farm14.3operational1.6
Paddock Woodsolar farm9.2operational3.7
Maidstone Road, Horsmonden - Paddock Solar Farmsolar farm49.9under construction6.2
Eckley Farms, Marden Solar Energy Farmsolar farm49.9approved, not built7.4
Pattenden Lane Solar PV Energysolar farm19application submitted8.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1781, 0.3596).