Offham Landfill Site (10.2 MW solar farm)

Offham Landfill Site is a 10.2 MW solar farm project in Tonbridge and Malling, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 March 2024; the record was last updated on 8 April 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10.2 MWsolar farm
under constructionstatus in REPD
8 April 2024record last updated
Tonbridge and Mallingcouncil area

Planning timeline

DateStage
20 April 2021Application submitted
13 October 2023Planning permission granted
1 March 2024Construction started

Project details

Technology
solar farm
Capacity
10.2 MW
Status (REPD)
under construction
Record last updated
8 April 2024
Operator or applicant
Infinis Limited
Planning authority
Tonbridge and Malling
Planning application reference
KCC/TM/0090/2021
Site area
19.1 ha
Address (REPD)
Offham Landfill Site, Teston Road, Offham, West Malling
Council area (by location)
Tonbridge and Malling
Time to decision
129 weeks
Name in REPD
Offham Landfill Site - Solar PV Array
REPD reference
9002

Who decides

ApplicationsTonbridge and MallingUK
Decided applications (solar, wind, battery)1210,236
Refused1 (8%)19%
Solar refused1 of 812%
Battery storage refused0 of 416%
Median time from submission to decision10.4 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Stangate West Landfill Site, Quarry Hill Road Solar Park & Batterysolar farm6application submitted4.4
Aylesford BESSbattery storage29operational6.9
Idleigh Court Road, New Ash Greensolar farm49.9application submitted9.1
West Kingdownsolar farm20application withdrawn9.4
Wouldham Road, Wouldhambattery storage7.5approved, not built9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.2904, 0.3661).