Energy Projects Near You

Renewable energy projects in Tonbridge and Malling

17 solar, wind or battery projects of 150 kW or more are located in Tonbridge and Malling (REPD, July 2026 extract): 5 pending, 7 approved but not running, 4 operational and 1 refused. The council refused 1 of 12 decided applications (8%; UK 19%), with a median 10 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

17projects in the council area
5awaiting a decision
7approved, not running
8%of decisions refused

How Tonbridge and Malling decides

ApplicationsTonbridge and MallingUK
Decided applications (solar, wind, battery)1210,236
Refused1 (8%)19%
Solar refused1 of 812%
Battery storage refused0 of 416%
Median time from submission to decision10.4 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Projects in Tonbridge and Malling

Projects of 1 MW and more (7)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Aylesford BESSbattery storagebattery storage29operationalupdated Mar 2026Sep 2017granted Dec 2017Mar 2026
Offham Landfill Sitesolar farmsolar farm10.2under constructionupdated Apr 2024Apr 2021granted Oct 2023Apr 2024
Wouldham Road, Wouldhambattery storagebattery storage7.5approved, not built may be out of dateupdated Dec 2021Nov 2021granted Jan 2022Dec 2021
Stangate West Landfill Site, Quarry Hill Road Solar Park & Batterysolar farmsolar farm6application submittedMay 2026——
Land off Ford Lanesolar farmsolar farm4.7operationalupdated Feb 2017Jul 2015granted Nov 2015Feb 2017
Biossence Solar Parksolar farmsolar farm4.5operationalupdated Mar 2013Apr 2011granted Jun 2011Mar 2013
Kingshill Solar Farmsolar farmsolar farm3operationalupdated Aug 2024Sep 2021granted Dec 2021Aug 2024
Smaller schemes under 1 MW, mostly rooftop solar (10)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Unit A Riverside Business Parkrooftop solarrooftop solar1approved, not builtupdated May 2022May 2022granted Jul 2022May 2022
Nutriblend House, Mills Roadrooftop solarrooftop solar0.3application submittedMay 2026——
The Tonbridge School Centre, London Roadrooftop solarrooftop solar0.3approved, not builtupdated Feb 2024Dec 2023granted Feb 2024Feb 2024
Platt Industrial Estate,Maidstone Road - Micro Energy Storage Facilitybattery storagebattery storage0.2application submittedupdated Nov 2024Oct 2024—Nov 2024
Mackenders Close - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Mar 2025Oct 2024granted Jan 2025Mar 2025
Corona Terrace And Hollow Lane - Micro Energy Storage Systembattery storagebattery storage0.2application submittedupdated Dec 2025Nov 2025—Dec 2025
Corona Terrace & Hollow Lane - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Jun 2026Nov 2025granted May 2026Jun 2026
Larkfield Leisure Centre, New Hythe Lanerooftop solarrooftop solar0.2approved, not builtupdated Jan 2025Oct 2024granted Dec 2024Jan 2025
Nizels Golf Club, Nizels Lanerooftop solarrooftop solar0.1refusedupdated Mar 2024Jan 2024refused Feb 2024Mar 2024
Stangate West Landfill Site, Quarry Hill Road Solar Park & Batterybattery storagebattery storage—application submittedMay 2026——

Postcode districts in Tonbridge and Malling

DistrictProjects within 10 kmPendingApprovedOperational
ME6248104
ME1923894
ME20213124
TN9252163
TN10277133
TN11255142
TN1515532

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Tonbridge and Malling by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.