Energy Projects Near You

Solar, wind and battery projects near New Romney (TN28)

8 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TN28 (Folkestone and Hythe): 1 is waiting for a planning decision, 3 approved but not yet running, 3 operational. The largest live scheme is St Mary in the Marsh (16 MW solar farm, application submitted on 28 March 2025, no decision recorded), 5.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8projects within 10 km
1awaiting a decision
3approved, not running
3operational

Projects within 10 km of TN28

Projects of 1 MW and more (6)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Sycamore Farmsolar farmsolar farm20operationalupdated Jul 2014Oct 2012granted Jan 2013Jul 2014Folkestone and Hythe5.3
St Mary in the Marshsolar farmsolar farm16application submittedupdated May 2025Mar 2025—May 2025Folkestone and Hythe5.4
Martin Farm, St. Marys Roadsolar farmsolar farm16approved, not builtupdated Mar 2026Mar 2025granted Jan 2026Mar 2026Folkestone and Hythe5.4
Dengemarsh Roadrooftop solarrooftop solar1operationalupdated Dec 2017Feb 2017granted Apr 2017Dec 2017Folkestone and Hythe6.0
Agney Farmwind farmwind farm8appeal withdrawnupdated Feb 2016Jan 2013—Feb 2016Folkestone and Hythe6.2
Little Cheyne Court Wind Farmwind farmwind farm59.8operationalupdated Jul 2009Nov 2002granted Oct 2005Jul 2009Folkestone and Hythe9.2
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
New Romney Wastewater Treatment Workssolar farmsolar farm0.2approved, not builtupdated Oct 2024Apr 2024granted Aug 2024Oct 2024Folkestone and Hythe0.2
The Marsh Academy, Station Roadrooftop solarrooftop solar0.4approved, not builtupdated Apr 2023Jan 2023granted Mar 2023Apr 2023Folkestone and Hythe0.6

Distance from the average position of the TN28 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm4121032.2
Rooftop solar201100.4
Wind farm200100

MW in pipeline: pending, approved and under-construction capacity.

How Folkestone and Hythe decides solar, wind and battery applications

Folkestone and Hythe has 9 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

All projects in Folkestone and Hythe

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.