Little Cheyne Court Wind Farm (59.8 MW)

Little Cheyne Court Wind Farm is a 59.8 MW wind farm project in Folkestone and Hythe, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 June 2009; the record was last updated on 9 July 2009.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

59.8 MWwind farm
operationalstatus in REPD
9 July 2009record last updated
Folkestone and Hythecouncil area

Planning timeline

DateStage
28 November 2002Application submitted
18 October 2005Refused by the planning authority
18 October 2005Planning permission granted
18 October 2005Appeal allowed
1 July 2008Construction started
1 June 2009Operational

Project details

Technology
wind farm
Capacity
59.8 MW
Status (REPD)
operational
Record last updated
9 July 2009
Operator or applicant
RWE npower
Planning authority
Folkestone and Hythe
Planning application reference
YO2/1278/SH
Turbines
26
Address (REPD)
Little Cheyne Court, Romney Marsh Near Lydd Kent
Council area (by location)
Folkestone and Hythe
Time to decision
151 weeks
REPD reference
3096

Who decides

Folkestone and Hythe has 9 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

Other large projects within 10 km

ProjectTypeMWStatuskm
Agney Farmwind farm8appeal withdrawn3.0
Sycamore Farmsolar farm20operational4.9
Martin Farm, St. Marys Roadsolar farm16approved, not built6.9
St Mary in the Marshsolar farm16application submitted7.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.9638, 0.8227).